DHS Coast Guard awards $3.5M dredging contract to Turner Strategic Technologies, LLC for Baltimore facility
Contract Overview
Contract Amount: $3,480,236 ($3.5M)
Contractor: Turner Strategic Technologies, LLC
Awarding Agency: Department of Homeland Security
Start Date: 2025-10-06
End Date: 2026-02-27
Contract Duration: 144 days
Daily Burn Rate: $24.2K/day
Competition Type: FULL AND OPEN COMPETITION AFTER EXCLUSION OF SOURCES
Number of Offers Received: 5
Pricing Type: FIRM FIXED PRICE
Sector: Construction
Official Description: MAINTENANCE DREDGING OF SYNCROLIFT U.S. COAST GUARD YARD BALTIMORE, MARYLAND
Place of Performance
Location: CURTIS BAY, ANNE ARUNDEL County, MARYLAND, 21226
State: Maryland Government Spending
Plain-Language Summary
Department of Homeland Security obligated $3.5 million to TURNER STRATEGIC TECHNOLOGIES, LLC for work described as: MAINTENANCE DREDGING OF SYNCROLIFT U.S. COAST GUARD YARD BALTIMORE, MARYLAND Key points: 1. Contract value appears reasonable for specialized marine infrastructure maintenance. 2. Full and open competition was utilized, suggesting a competitive bidding process. 3. Potential risks include project delays or unforeseen environmental challenges. 4. Performance will be assessed against contract requirements for dredging depth and disposal. 5. This contract falls within the broader Defense and Infrastructure maintenance sector. 6. The award is a delivery order under a larger contract vehicle.
Value Assessment
Rating: good
The contract value of $3.5 million for maintenance dredging is within a typical range for such specialized maritime infrastructure work. Benchmarking against similar dredging contracts for naval or port facilities suggests this is a fair price, assuming the scope of work and environmental conditions are comparable. The firm-fixed-price structure helps control costs for the government.
Cost Per Unit: N/A
Competition Analysis
Competition Level: full-and-open
The contract was awarded under 'Full and Open Competition After Exclusion of Sources,' indicating that while initial solicitations might have had limitations, the final award was made after a broad competitive process. Five bids were received, demonstrating a healthy level of interest and competition for this specialized service.
Taxpayer Impact: A competitive process with multiple bidders generally leads to better price discovery and potentially lower costs for taxpayers compared to sole-source or limited competition awards.
Public Impact
The U.S. Coast Guard facility in Baltimore, Maryland, will benefit from improved operational capacity. Services delivered include essential maintenance dredging to ensure safe navigation and access. The geographic impact is localized to the U.S. Coast Guard Yard in Baltimore, Maryland. Workforce implications include employment for skilled maritime labor and support personnel.
Waste & Efficiency Indicators
Waste Risk Score: 50 / 10
Warning Flags
- Potential for scope creep if unforeseen subsurface conditions are encountered.
- Dependence on favorable weather conditions for efficient execution of dredging operations.
- Ensuring proper environmental compliance during dredging and material disposal.
Positive Signals
- Firm-fixed-price contract provides cost certainty for the government.
- Multiple bids received indicate a competitive market for these services.
- Delivery order structure allows for flexibility within a pre-established contract.
Sector Analysis
This contract falls within the construction and maintenance sector, specifically focusing on marine infrastructure. The market for specialized dredging services is competitive, with a number of firms possessing the necessary equipment and expertise. Spending on maintaining critical maritime facilities like Coast Guard yards is essential for national security and economic activity, with comparable contracts often awarded for port improvements and naval base upkeep.
Small Business Impact
The contract data does not indicate any specific small business set-aside provisions. Given the specialized nature of marine dredging, it is possible that larger, more experienced firms dominate this market. Subcontracting opportunities for small businesses may exist, but are not explicitly detailed in the provided information.
Oversight & Accountability
The contract is subject to standard federal procurement oversight. The U.S. Coast Guard, as part of the Department of Homeland Security, has established oversight mechanisms. Accountability will be ensured through performance monitoring against contract deliverables and adherence to the firm-fixed-price terms. Transparency is facilitated by the public nature of federal contract awards.
Related Government Programs
- U.S. Coast Guard Base Maintenance
- Port and Harbor Dredging Projects
- Maritime Infrastructure Modernization
- Naval Facilities Engineering Command Contracts
Risk Flags
- Potential for unforeseen subsurface conditions
- Environmental compliance risks
- Weather-related delays
Tags
construction, maintenance, dredging, marine-infrastructure, department-of-homeland-security, u.s.-coast-guard, baltimore, maryland, full-and-open-competition, firm-fixed-price, delivery-order, commercial-and-institutional-building-construction
Frequently Asked Questions
What is this federal contract paying for?
Department of Homeland Security awarded $3.5 million to TURNER STRATEGIC TECHNOLOGIES, LLC. MAINTENANCE DREDGING OF SYNCROLIFT U.S. COAST GUARD YARD BALTIMORE, MARYLAND
Who is the contractor on this award?
The obligated recipient is TURNER STRATEGIC TECHNOLOGIES, LLC.
Which agency awarded this contract?
Awarding agency: Department of Homeland Security (U.S. Coast Guard).
What is the total obligated amount?
The obligated amount is $3.5 million.
What is the period of performance?
Start: 2025-10-06. End: 2026-02-27.
What is the track record of Turner Strategic Technologies, LLC in performing similar marine construction or dredging contracts?
Information regarding Turner Strategic Technologies, LLC's specific track record in marine construction or dredging is not detailed in the provided data. A comprehensive assessment would require reviewing their past performance on similar federal contracts, including client feedback, project completion history, and any documented issues or successes. Federal procurement databases and past performance reviews would be the primary sources for this analysis. Without this specific data, it's difficult to definitively assess their experience level in this niche area, though their selection suggests they met the government's criteria at the time of award.
How does the awarded amount compare to the estimated cost or budget for this dredging project?
The provided data does not include the government's estimated cost or budget for this maintenance dredging project. The awarded amount of $3,480,236 represents the price agreed upon through the competitive bidding process. To assess value for money, this figure would ideally be compared against an independent government estimate or benchmark data from similar dredging projects. The fact that five bids were received suggests the price was competitive, but without the estimated cost, a direct comparison of the award to the budget is not possible from the given information.
What are the primary risks associated with this specific dredging contract, beyond general project risks?
Specific risks for this dredging contract include encountering unforeseen subsurface obstructions (e.g., buried debris, hard rock) that could increase costs or cause delays, as well as potential environmental challenges related to sediment composition, disposal regulations, and marine life protection. Weather conditions in Baltimore harbor can also impact the schedule. Furthermore, ensuring the precise depth and width specifications are met consistently across the entire work area is critical for the Coast Guard's operational needs. The firm-fixed-price nature means the contractor bears the risk of cost overruns due to these factors, up to certain contractual limits.
What is the historical spending pattern for maintenance dredging at U.S. Coast Guard facilities, and how does this award fit?
Historical spending on maintenance dredging at U.S. Coast Guard facilities can vary significantly based on the size and age of the facility, its location, and the frequency of required maintenance. Facilities like the Baltimore Yard, which are critical operational hubs, likely undergo regular dredging to maintain navigable depths. This $3.5 million award appears to be a significant but potentially periodic investment. Analyzing past contracts for similar Coast Guard yards or other maritime facilities would provide context on the typical scale and frequency of such expenditures, helping to determine if this award represents a standard or exceptional level of investment.
What are the key performance indicators (KPIs) that will be used to evaluate the success of this contract?
Key performance indicators for this maintenance dredging contract will likely focus on adherence to the specified dredging depths and widths, timely completion of the project within the defined period (February 27, 2026), and proper disposal of dredged materials in accordance with environmental regulations. The contractor's ability to minimize disruption to ongoing Coast Guard operations at the yard will also be a factor. Successful completion will be measured by the government's verification that the required navigational clearances have been achieved and maintained, and that all contractual obligations, including environmental compliance, have been met.
Industry Classification
NAICS: Construction › Nonresidential Building Construction › Commercial and Institutional Building Construction
Product/Service Code: MAINT, REPAIR, ALTER REAL PROPERTY › MAINT, ALTER, REPAIR NONBUILDINGS
Competition & Pricing
Extent Competed: FULL AND OPEN COMPETITION AFTER EXCLUSION OF SOURCES
Solicitation Procedures: SUBJECT TO MULTIPLE AWARD FAIR OPPORTUNITY
Offers Received: 5
Pricing Type: FIRM FIXED PRICE (J)
Evaluated Preference: NONE
Contractor Details
Address: 7440 CENTRAL BUSINESS PARK DR, NORFOLK, VA, 23513
Business Categories: 8(a) Program Participant, Category Business, Corporate Entity Not Tax Exempt, Hispanic American Owned Business, Limited Liability Corporation, Minority Owned Business, Self-Certified Small Disadvantaged Business, Service Disabled Veteran Owned Business, Small Business, Special Designations, U.S.-Owned Business, Veteran Owned Business
Financial Breakdown
Contract Ceiling: $3,480,236
Exercised Options: $3,480,236
Current Obligation: $3,480,236
Contract Characteristics
Commercial Item: COMMERCIAL PRODUCTS/SERVICES PROCEDURES NOT USED
Cost or Pricing Data: NO
Parent Contract
Parent Award PIID: 70Z08318DPCR07800
IDV Type: IDC
Timeline
Start Date: 2025-10-06
Current End Date: 2026-02-27
Potential End Date: 2026-02-27 12:10:32
Last Modified: 2026-01-29
More Contracts from Turner Strategic Technologies, LLC
- X031 NSN Bldg W-143 Replace Freight Elevators — $18.7M (Department of Defense)
- Provide ALL Labor, Material, Equipment, Transportation and Supervision Required to Construct NEW Parking LOT and Storm Water Permit Compliance and Repairs @ U. S. Coast Guard Base Portsmouth, Portsmouth, VA — $6.4M (Department of Homeland Security)
- Major M&R Hvac Systems AT Communications Command, Chesapeake, VA — $4.4M (Department of Homeland Security)
View all Turner Strategic Technologies, LLC federal contracts →
Other Department of Homeland Security Contracts
- THE United States Coast Guard HAS a Requirement to Procure UP to Twenty-Six (26) Fast Response Cutters (frcs) on a Firm Fixed Price (FFP) Basis With an Economic Price Adjustment (EPA). Phase II of the FRC Program Will Complete the Fleet for a Total of 58 Cutters — $2.1B (Bollinger Shipyards Lockport, L.L.C.)
- Design and Construct NEW Vertical Barrier and Power Distribution, Lighting, Cameras, Equipment Shelters and Linear Ground Detection System (lgds) in Hildago County, NM — $1.8B (Fisher Sand & Gravel CO)
- Production&delivery of National Security Cutter (NSC) 6 — $1.7B (Huntington Ingalls Incorporated)
- YUM-2 Vertical Border and Waterborne Barrier Construction — $1.7B (Fisher Sand & Gravel CO)
- Construct Vertical Border Barrier — $1.6B (Fisher Sand & Gravel CO)