Fort Carson Barracks Construction Awarded to Sundt Construction for $20.86M Under Full and Open Competition

Contract Overview

Contract Amount: $20,859,461 ($20.9M)

Contractor: Sundt Construction, Inc.

Awarding Agency: Department of Defense

Start Date: 2008-03-31

End Date: 2009-11-17

Contract Duration: 596 days

Daily Burn Rate: $35.0K/day

Competition Type: FULL AND OPEN COMPETITION

Number of Offers Received: 2

Pricing Type: FIRM FIXED PRICE

Sector: Construction

Official Description: MIL - CONSTRUCTION OF NORTH BARRACKS, FORT CARSON, CO

Place of Performance

Location: COLORADO SPRINGS, EL PASO County, COLORADO, 80913

State: Colorado Government Spending

Plain-Language Summary

Department of Defense obligated $20.9 million to SUNDT CONSTRUCTION, INC. for work described as: MIL - CONSTRUCTION OF NORTH BARRACKS, FORT CARSON, CO Key points: 1. The contract awarded to Sundt Construction, Inc. for $20.86 million addresses a critical infrastructure need for the Department of the Army at Fort Carson. 2. Full and open competition was utilized, suggesting a robust price discovery process and potential for competitive pricing. 3. The project falls within the Commercial and Institutional Building Construction sector, a common area for federal infrastructure spending. 4. The firm-fixed-price contract type shifts cost risk to the contractor, which can be beneficial for budget predictability.

Value Assessment

Rating: good

The award amount of $20.86 million for barracks construction appears reasonable given the project scope and duration. Benchmarking against similar military construction projects would provide a more definitive assessment of value.

Cost Per Unit: N/A

Competition Analysis

Competition Level: full-and-open

The use of full and open competition indicates that multiple bidders were likely considered, promoting a competitive environment that should drive favorable pricing. The award was made via a delivery order, suggesting it was part of a larger indefinite-delivery/indefinite-quantity (IDIQ) contract or similar vehicle.

Taxpayer Impact: The competitive bidding process is expected to have secured a fair price for taxpayers, maximizing the value of the federal investment in military infrastructure.

Public Impact

Enhances living conditions and operational readiness for soldiers stationed at Fort Carson. Supports the local economy in Colorado through construction jobs and related services. Represents a significant federal investment in military infrastructure modernization.

Waste & Efficiency Indicators

Waste Risk Score: 50 / 10

Warning Flags

  • Potential for cost overruns if unforeseen site conditions arise, despite firm-fixed-price.
  • Schedule delays could impact soldier readiness if not managed effectively.

Positive Signals

  • Addresses a clear military requirement for improved barracks.
  • Competitive award process likely resulted in a fair market price.
  • Firm-fixed-price contract provides budget certainty.

Sector Analysis

This project falls under the Commercial and Institutional Building Construction sector, a significant area of federal spending for infrastructure development. Benchmarks for similar military construction projects would be necessary for a precise comparison, but the award amount appears within a typical range for such endeavors.

Small Business Impact

The data indicates that small businesses were not directly awarded this contract, as Sundt Construction, Inc. is a large business. Further analysis would be needed to determine if small businesses participated as subcontractors.

Oversight & Accountability

The Department of the Army, under the Department of Defense, is responsible for overseeing this construction project. Standard procurement regulations and oversight mechanisms should be in place to ensure contract compliance and quality.

Related Government Programs

  • Commercial and Institutional Building Construction
  • Department of Defense Contracting
  • Department of the Army Programs

Risk Flags

  • Potential for schedule slippage impacting troop readiness.
  • Unforeseen site conditions could lead to change orders.
  • Quality control effectiveness is not explicitly detailed.
  • Reliance on a single large prime contractor.

Tags

commercial-and-institutional-building-co, department-of-defense, co, delivery-order, 10m-plus

Frequently Asked Questions

What is this federal contract paying for?

Department of Defense awarded $20.9 million to SUNDT CONSTRUCTION, INC.. MIL - CONSTRUCTION OF NORTH BARRACKS, FORT CARSON, CO

Who is the contractor on this award?

The obligated recipient is SUNDT CONSTRUCTION, INC..

Which agency awarded this contract?

Awarding agency: Department of Defense (Department of the Army).

What is the total obligated amount?

The obligated amount is $20.9 million.

What is the period of performance?

Start: 2008-03-31. End: 2009-11-17.

What was the total number of bids received during the full and open competition, and how did the winning bid compare to the government estimate?

The provided data does not specify the number of bids received or the government estimate. Obtaining this information would be crucial for a thorough assessment of the competition's effectiveness and the value achieved. Understanding the bid spread can indicate the level of competition and whether the final price was significantly lower than anticipated.

Are there any specific performance metrics or quality assurance measures included in the contract to mitigate construction risks?

While the contract type is firm-fixed-price, which shifts cost risk, specific performance metrics and quality assurance measures are not detailed in the provided data. Effective oversight by the Department of the Army is critical to ensure the construction meets required standards and timelines, mitigating risks related to quality and potential delays.

How does the per-square-foot cost of this barracks construction compare to similar projects in the region or other military installations?

A precise per-square-foot cost comparison is not possible without detailed project specifications (e.g., square footage, amenities). However, the total award of $20.86 million for a 596-day duration project suggests a substantial investment. Benchmarking against similar military barracks construction would be necessary to evaluate cost-effectiveness.

Industry Classification

NAICS: ConstructionNonresidential Building ConstructionCommercial and Institutional Building Construction

Product/Service Code: CONSTRUCT OF STRUCTURES/FACILITIESCONSTRUCTION OF BUILDINGS

Competition & Pricing

Extent Competed: FULL AND OPEN COMPETITION

Offers Received: 2

Pricing Type: FIRM FIXED PRICE (J)

Evaluated Preference: NONE

Contractor Details

Parent Company: THE Sundt Companies Inc (UEI: 073354982)

Address: 2620 S 55TH ST, TEMPE, AZ, 85282

Business Categories: Category Business, Corporate Entity Not Tax Exempt, Not Designated a Small Business, Subchapter S Corporation

Financial Breakdown

Contract Ceiling: $20,859,461

Exercised Options: $20,859,461

Current Obligation: $20,859,461

Contract Characteristics

Commercial Item: COMMERCIAL ITEM PROCEDURES NOT USED

Cost or Pricing Data: NO

Parent Contract

Parent Award PIID: W912DQ08D0008

IDV Type: IDC

Timeline

Start Date: 2008-03-31

Current End Date: 2009-11-17

Potential End Date: 2009-11-17 00:00:00

Last Modified: 2021-04-29

More Contracts from Sundt Construction, Inc.

View all Sundt Construction, Inc. federal contracts →

Other Department of Defense Contracts

View all Department of Defense contracts →

Explore Related Government Spending