Interior's $6M Marys Lake Runner Replacement Contract Awarded to American Hydro LLC

Contract Overview

Contract Amount: $6,075,061 ($6.1M)

Contractor: American Hydro LLC

Awarding Agency: Department of the Interior

Start Date: 2021-03-24

End Date: 2024-10-25

Contract Duration: 1,311 days

Daily Burn Rate: $4.6K/day

Competition Type: FULL AND OPEN COMPETITION

Number of Offers Received: 4

Pricing Type: FIRM FIXED PRICE

Sector: Construction

Official Description: MARYS LAKE RUNNER REPLACEMENT AND TURBINE OVERHAUL

Place of Performance

Location: ESTES PARK, LARIMER County, COLORADO, 80517

State: Colorado Government Spending

Plain-Language Summary

Department of the Interior obligated $6.1 million to AMERICAN HYDRO LLC for work described as: MARYS LAKE RUNNER REPLACEMENT AND TURBINE OVERHAUL Key points: 1. Contract awarded for turbine overhaul and runner replacement at Marys Lake. 2. American Hydro LLC secured the $6.075 million contract. 3. The project falls under 'Other Heavy and Civil Engineering Construction'. 4. Full and open competition was utilized for this procurement.

Value Assessment

Rating: good

The contract value of $6.075 million appears reasonable for a complex heavy civil engineering project involving turbine overhaul and replacement. Benchmarking against similar large-scale hydropower infrastructure projects would provide a more precise assessment.

Cost Per Unit: N/A

Competition Analysis

Competition Level: full-and-open

The use of full and open competition suggests a robust price discovery process. This method allows multiple qualified bidders to submit proposals, theoretically leading to more competitive pricing and better value for the government.

Taxpayer Impact: The competitive bidding process aims to ensure taxpayer funds are used efficiently for this critical infrastructure upgrade.

Public Impact

Ensures continued reliable operation of the Marys Lake power facility. Supports infrastructure modernization within the Bureau of Reclamation. Potential for job creation in the heavy civil engineering sector.

Waste & Efficiency Indicators

Waste Risk Score: 50 / 10

Warning Flags

Positive Signals

Sector Analysis

This contract falls within the heavy and civil engineering construction sector, specifically related to hydropower infrastructure. Spending in this sector is often driven by the need for infrastructure maintenance, upgrades, and new development, with significant capital investment required.

Small Business Impact

The data does not indicate whether small businesses were involved as subcontractors or prime contractors. Further analysis would be needed to determine the extent of small business participation in this procurement.

Oversight & Accountability

The Bureau of Reclamation, under the Department of the Interior, is responsible for overseeing this contract. Standard oversight mechanisms for construction projects, including progress monitoring and quality assurance, would be expected.

Related Government Programs

Risk Flags

Tags

other-heavy-and-civil-engineering-constr, department-of-the-interior, co, definitive-contract, 1m-plus

Frequently Asked Questions

What is this federal contract paying for?

Department of the Interior awarded $6.1 million to AMERICAN HYDRO LLC. MARYS LAKE RUNNER REPLACEMENT AND TURBINE OVERHAUL

Who is the contractor on this award?

The obligated recipient is AMERICAN HYDRO LLC.

Which agency awarded this contract?

Awarding agency: Department of the Interior (Bureau of Reclamation).

What is the total obligated amount?

The obligated amount is $6.1 million.

What is the period of performance?

Start: 2021-03-24. End: 2024-10-25.

What is the historical performance of American Hydro LLC on similar federal contracts?

Assessing American Hydro LLC's past performance on comparable federal contracts is crucial for understanding their reliability and capability. Reviewing past project completion times, adherence to budget, and quality of work on similar turbine overhaul and replacement projects would provide valuable insights into their suitability for this undertaking and potential risks.

Are there any specific environmental or operational risks associated with this turbine overhaul?

Turbine overhauls can present environmental risks such as potential spills of lubricants or hydraulic fluids, and operational risks related to temporary power generation disruption. The contract should detail mitigation strategies for these risks, including containment measures and contingency plans for power supply, to ensure minimal environmental impact and continued service.

How does the firm-fixed-price structure impact the government's ability to manage costs during unforeseen issues?

A firm-fixed-price contract generally shifts cost risk to the contractor, providing budget certainty for the government. However, unforeseen issues during complex construction can lead to change orders, potentially increasing costs. Robust contract management and clear scope definition are essential to minimize the impact of such changes on the overall project expenditure.

Industry Classification

NAICS: ConstructionOther Heavy and Civil Engineering ConstructionOther Heavy and Civil Engineering Construction

Product/Service Code: MAINT, REPAIR, ALTER REAL PROPERTYMAINT, ALTER, REPAIR NONBUILDINGS

Competition & Pricing

Extent Competed: FULL AND OPEN COMPETITION

Solicitation Procedures: NEGOTIATED PROPOSAL/QUOTE

Solicitation ID: 140R6020R0005

Offers Received: 4

Pricing Type: FIRM FIXED PRICE (J)

Evaluated Preference: NONE

Contractor Details

Parent Company: Wärtsilä OYJ ABP

Address: 135 STONEWOOD RD, YORK, PA, 17402

Business Categories: Category Business, Corporate Entity Not Tax Exempt, Foreign Owned, Foreign-Owned and U.S.-Incorporated Business, Manufacturer of Goods, Not Designated a Small Business, Special Designations

Financial Breakdown

Contract Ceiling: $6,075,061

Exercised Options: $6,075,061

Current Obligation: $6,075,061

Actual Outlays: $4,979,382

Contract Characteristics

Commercial Item: COMMERCIAL PRODUCTS/SERVICES PROCEDURES NOT USED

Cost or Pricing Data: NO

Timeline

Start Date: 2021-03-24

Current End Date: 2024-10-25

Potential End Date: 2024-10-25 00:00:00

Last Modified: 2026-03-26

More Contracts from American Hydro LLC

View all American Hydro LLC federal contracts →

Other Department of the Interior Contracts

View all Department of the Interior contracts →

Explore Related Government Spending