DOD's $16.4M Hardaway Construction Contract for Garden Hills Elementary Faces Scrutiny
Contract Overview
Contract Amount: $16,386,299 ($16.4M)
Contractor: Hardaway Construction Corp.
Awarding Agency: Department of Defense
Start Date: 2009-02-12
End Date: 2011-05-25
Contract Duration: 832 days
Daily Burn Rate: $19.7K/day
Competition Type: FULL AND OPEN COMPETITION
Number of Offers Received: 8
Pricing Type: FIRM FIXED PRICE
Sector: Construction
Official Description: FTC GARDEN HILLS ELEMENTARY PR&C FOR CON
Place of Performance
Location: FORT CAMPBELL, LAUREL County, KENTUCKY, 42223
State: Kentucky Government Spending
Plain-Language Summary
Department of Defense obligated $16.4 million to HARDAWAY CONSTRUCTION CORP. for work described as: FTC GARDEN HILLS ELEMENTARY PR&C FOR CON Key points: 1. Contract awarded to Hardaway Construction Corp. for $16.4 million. 2. Full and open competition was utilized. 3. Project duration was 832 days. 4. The contract falls under Commercial and Institutional Building Construction. 5. The award was made by the Department of the Army.
Value Assessment
Rating: fair
The contract value of $16.4 million for a school construction project appears within a reasonable range for similar large-scale institutional builds. However, without specific project scope details, a precise comparison is difficult.
Cost Per Unit: N/A
Competition Analysis
Competition Level: full-and-open
The use of full and open competition suggests a robust price discovery process. This method typically aims to secure the best value by allowing all qualified contractors to bid.
Taxpayer Impact: Taxpayer funds were utilized through a competitive bidding process, aiming for cost-effectiveness in constructing educational facilities.
Public Impact
Construction of an elementary school impacts local communities and educational infrastructure. The contract's duration and value suggest a significant public works project. Transparency in the bidding process is crucial for public trust in government spending.
Waste & Efficiency Indicators
Waste Risk Score: 50 / 10
Warning Flags
- Lack of specific performance metrics.
- Potential for cost overruns in long-term construction projects.
- Limited information on project success beyond completion.
Positive Signals
- Utilized full and open competition.
- Awarded by a major federal agency (DOD).
- Clear contract type (Firm Fixed Price).
Sector Analysis
This contract falls within the construction sector, specifically commercial and institutional building. Benchmarks for school construction vary widely by region and scope, but large federal projects often involve significant investment.
Small Business Impact
The data indicates this contract was not specifically set aside for small businesses, and no information is provided on small business subcontracting. Further analysis would be needed to determine small business participation.
Oversight & Accountability
Oversight would typically involve the Department of the Army's contracting officers and potentially inspectors general to ensure adherence to contract terms and quality standards.
Related Government Programs
- Commercial and Institutional Building Construction
- Department of Defense Contracting
- Department of the Army Programs
Risk Flags
- Potential for cost overruns.
- Lack of detailed performance metrics.
- Limited post-completion quality assessment data.
- Unknown small business participation.
Tags
commercial-and-institutional-building-co, department-of-defense, ky, dca, 10m-plus
Frequently Asked Questions
What is this federal contract paying for?
Department of Defense awarded $16.4 million to HARDAWAY CONSTRUCTION CORP.. FTC GARDEN HILLS ELEMENTARY PR&C FOR CON
Who is the contractor on this award?
The obligated recipient is HARDAWAY CONSTRUCTION CORP..
Which agency awarded this contract?
Awarding agency: Department of Defense (Department of the Army).
What is the total obligated amount?
The obligated amount is $16.4 million.
What is the period of performance?
Start: 2009-02-12. End: 2011-05-25.
What was the final cost compared to the initial bid, and were there any change orders that significantly impacted the budget?
The provided data shows the award amount but not the final cost or details on change orders. A comprehensive review would require access to contract modifications and final payment records to assess budget adherence and identify any significant deviations from the initial bid.
How did the final construction quality and functionality compare to the contract's specifications and the needs of the school?
The data does not include information on the quality of the completed construction or its alignment with the school's functional requirements. Post-completion inspections, user feedback, and facility assessments would be necessary to evaluate the effectiveness and quality of the delivered project.
Were there any performance issues or disputes during the contract period that affected the timeline or cost?
The provided data does not detail any performance issues or disputes. Investigating contract performance would involve reviewing contractor performance reports, any claims filed, or litigation records associated with Hardaway Construction Corp. during the contract's execution.
Industry Classification
NAICS: Construction › Nonresidential Building Construction › Commercial and Institutional Building Construction
Product/Service Code: CONSTRUCT OF STRUCTURES/FACILITIES › CONSTRUCTION OF BUILDINGS
Competition & Pricing
Extent Competed: FULL AND OPEN COMPETITION
Solicitation Procedures: NEGOTIATED PROPOSAL/QUOTE
Solicitation ID: W912QR09R0007
Offers Received: 8
Pricing Type: FIRM FIXED PRICE (J)
Evaluated Preference: NONE
Contractor Details
Parent Company: Hardaway Group Inc (UEI: 131056467)
Address: 615 MAIN ST, NASHVILLE, TN, 90
Business Categories: Category Business, Corporate Entity Not Tax Exempt, Not Designated a Small Business, Special Designations, U.S.-Owned Business
Financial Breakdown
Contract Ceiling: $16,386,299
Exercised Options: $16,386,299
Current Obligation: $16,386,299
Contract Characteristics
Cost or Pricing Data: NO
Timeline
Start Date: 2009-02-12
Current End Date: 2011-05-25
Potential End Date: 2011-05-25 00:00:00
Last Modified: 2010-12-20
Other Department of Defense Contracts
- Federal Contract — $51.3B (Humana Government Business Inc)
- Lrip LOT 12 Advance Acquisition Contract — $35.1B (Lockheed Martin Corporation)
- SSN 802 and 803 Long Lead Time Material — $34.7B (Electric Boat Corporation)
- 200204!008532!1700!AF600 !naval AIR Systems Command !N0001902C3002 !A!N! !N! !20011026!20120430!008016958!008016958!834951691!n!lockheed Martin Corporation !lockheed Blvd !fort Worth !tx!76108!27000!439!48!fort Worth !tarrant !texas !+000026000000!n!n!018981928201!ac15!rdte/Aircraft-Eng/Manuf Develop !a1a!airframes and Spares !2ama!jast/Jsf !336411!E! !3! ! ! ! ! !99990909!B! ! !A! !a!n!r!2!002!n!1a!a!n!z! ! !N!C!N! ! ! !a!a!a!a!000!a!c!n! ! ! !Y! !N00019!0001! — $34.2B (Lockheed Martin Corporation)
- KC-X Modernization Program — $32.0B (THE Boeing Company)