DOD Awards $13M Design/Build Security Facility to Scott Alliance, Inc. at Scott AFB
Contract Overview
Contract Amount: $12,999,665 ($13.0M)
Contractor: Scott Alliance, Inc., a Joint Venture
Awarding Agency: Department of Defense
Start Date: 2008-04-15
End Date: 2011-10-31
Contract Duration: 1,294 days
Daily Burn Rate: $10.0K/day
Competition Type: FULL AND OPEN COMPETITION
Number of Offers Received: 5
Pricing Type: FIRM FIXED PRICE
Sector: Construction
Official Description: DESIGN/BUILD SECURITY FORCES OPERATIONS FACILITY, SCOTT AFB, IL
Place of Performance
Location: SCOTT AFB, ST. CLAIR County, ILLINOIS, 62225
State: Illinois Government Spending
Plain-Language Summary
Department of Defense obligated $13.0 million to SCOTT ALLIANCE, INC., A JOINT VENTURE for work described as: DESIGN/BUILD SECURITY FORCES OPERATIONS FACILITY, SCOTT AFB, IL Key points: 1. Contract awarded to Scott Alliance, Inc., a joint venture. 2. Project involves design and construction of a security forces operations facility. 3. Full and open competition was utilized for this award. 4. The contract was firm fixed price, indicating price certainty. 5. The facility is located at Scott Air Force Base, Illinois.
Value Assessment
Rating: good
The award amount of $12,999,665 appears reasonable for a design/build security facility of this nature. Benchmarking against similar construction projects would provide a more definitive assessment.
Cost Per Unit: N/A
Competition Analysis
Competition Level: full-and-open
The contract was awarded under full and open competition, suggesting a robust price discovery process. This method typically leads to more competitive pricing.
Taxpayer Impact: The use of full and open competition is generally beneficial for taxpayers, as it encourages multiple bidders to offer their best prices.
Public Impact
Enhances security force capabilities at Scott AFB. Supports military infrastructure development. Creates construction jobs in Illinois. Ensures modern facilities for critical operations.
Waste & Efficiency Indicators
Waste Risk Score: 50 / 10
Warning Flags
- No small business participation noted.
Positive Signals
- Full and open competition utilized.
- Firm fixed price contract provides cost certainty.
Sector Analysis
This contract falls under the Commercial and Institutional Building Construction sector. Spending in this sector is crucial for maintaining and upgrading federal infrastructure.
Small Business Impact
The data indicates that small business participation was not a factor in this specific award. Further analysis would be needed to determine if this is a trend or an isolated instance.
Oversight & Accountability
The contract was awarded by the Department of the Army, part of the Department of Defense. Standard oversight mechanisms for federal construction projects would apply.
Related Government Programs
- Commercial and Institutional Building Construction
- Department of Defense Contracting
- Department of the Army Programs
Risk Flags
- No small business participation.
- Potential for unforeseen site conditions in construction.
- Long contract duration increases risk exposure.
Tags
commercial-and-institutional-building-co, department-of-defense, il, dca, 10m-plus
Frequently Asked Questions
What is this federal contract paying for?
Department of Defense awarded $13.0 million to SCOTT ALLIANCE, INC., A JOINT VENTURE. DESIGN/BUILD SECURITY FORCES OPERATIONS FACILITY, SCOTT AFB, IL
Who is the contractor on this award?
The obligated recipient is SCOTT ALLIANCE, INC., A JOINT VENTURE.
Which agency awarded this contract?
Awarding agency: Department of Defense (Department of the Army).
What is the total obligated amount?
The obligated amount is $13.0 million.
What is the period of performance?
Start: 2008-04-15. End: 2011-10-31.
What was the competitive landscape like during the bidding process?
The contract was awarded under full and open competition, indicating that all responsible sources were permitted to submit bids. While the specific number of bids received isn't detailed, this method generally fosters a competitive environment, allowing the government to select the best value proposal based on price and other factors.
Are there any potential cost overruns or risks associated with this project?
The contract is firm fixed price, which shifts most of the cost risk to the contractor. However, risks could still arise from unforeseen site conditions, design changes, or contractor performance issues. The duration of the contract (1294 days) suggests a complex project where diligent oversight is necessary to mitigate potential delays and cost impacts.
How does this project contribute to the overall effectiveness of security forces at Scott AFB?
The design/build security forces operations facility is intended to provide modern, functional infrastructure for security personnel. This likely includes improved workspaces, training areas, and administrative support, which can enhance operational readiness, morale, and the overall effectiveness of the security forces stationed at Scott Air Force Base.
Industry Classification
NAICS: Construction › Nonresidential Building Construction › Commercial and Institutional Building Construction
Product/Service Code: CONSTRUCT OF STRUCTURES/FACILITIES › CONSTRUCTION OF BUILDINGS
Competition & Pricing
Extent Competed: FULL AND OPEN COMPETITION
Solicitation Procedures: NEGOTIATED PROPOSAL/QUOTE
Solicitation ID: W912QR08R0005
Offers Received: 5
Pricing Type: FIRM FIXED PRICE (J)
Evaluated Preference: NONE
Contractor Details
Address: 33 W MONROE STE 2100, CHICAGO, IL, 90
Business Categories: Category Business, Small Business, Small Disadvantaged Business, Special Designations, U.S.-Owned Business, Woman Owned Business
Financial Breakdown
Contract Ceiling: $12,999,665
Exercised Options: $12,999,665
Current Obligation: $12,999,665
Contract Characteristics
Cost or Pricing Data: NO
Timeline
Start Date: 2008-04-15
Current End Date: 2011-10-31
Potential End Date: 2011-10-31 00:00:00
Last Modified: 2011-01-26
Other Department of Defense Contracts
- Federal Contract — $51.3B (Humana Government Business Inc)
- Lrip LOT 12 Advance Acquisition Contract — $35.1B (Lockheed Martin Corporation)
- SSN 802 and 803 Long Lead Time Material — $34.7B (Electric Boat Corporation)
- 200204!008532!1700!AF600 !naval AIR Systems Command !N0001902C3002 !A!N! !N! !20011026!20120430!008016958!008016958!834951691!n!lockheed Martin Corporation !lockheed Blvd !fort Worth !tx!76108!27000!439!48!fort Worth !tarrant !texas !+000026000000!n!n!018981928201!ac15!rdte/Aircraft-Eng/Manuf Develop !a1a!airframes and Spares !2ama!jast/Jsf !336411!E! !3! ! ! ! ! !99990909!B! ! !A! !a!n!r!2!002!n!1a!a!n!z! ! !N!C!N! ! ! !a!a!a!a!000!a!c!n! ! ! !Y! !N00019!0001! — $34.2B (Lockheed Martin Corporation)
- KC-X Modernization Program — $32.0B (THE Boeing Company)