Charenton Floodgate, ST. Mary Parish, LA
Contract Overview
Contract Amount: $55,868,262 ($55.9M)
Contractor: Archer Western Construction, LLC
Awarding Agency: Department of Defense
Start Date: 2022-10-05
End Date: 2025-08-12
Contract Duration: 1,042 days
Daily Burn Rate: $53.6K/day
Official Description: CHARENTON FLOODGATE, ST. MARY PARISH, LA
Place of Performance
Location: Louisiana, 70340