Preconstruction Services for LPV 145 ECI, ST Bernard Parish, LA
Contract Overview
Contract Amount: $236,874,275 ($236.9M)
Contractor: Chalmette Levee Constructors, a Joint Venture
Awarding Agency: Department of Defense
Start Date: 2009-07-13
End Date: 2011-06-01
Contract Duration: 688 days
Daily Burn Rate: $344.3K/day
Official Description: PRECONSTRUCTION SERVICES FOR LPV 145 ECI, ST BERNARD PARISH, LA
Place of Performance
Location: Louisiana, 70001