Corpus Christi Ship Channel, Texas, Inner Basin to Viola, Maintenance Dredging. Schedule NO. 1 Consists of Dredging Approximately 2.5 Million Cubic Yards 3 Options Total an Additional 640,000 Cubic Yards
Contract Overview
Contract Amount: $22,517,680 ($22.5M)
Contractor: Orion Marine Construction, Inc.
Awarding Agency: Department of Defense
Start Date: 2024-10-05
End Date: 2025-10-10
Contract Duration: 370 days
Daily Burn Rate: $60.9K/day
Official Description: CORPUS CHRISTI SHIP CHANNEL, TEXAS, INNER BASIN TO VIOLA, MAINTENANCE DREDGING. SCHEDULE NO. 1 CONSISTS OF DREDGING APPROXIMATELY 2.5 MILLION CUBIC YARDS 3 OPTIONS TOTAL AN ADDITIONAL 640,000 CUBIC YARDS.
Place of Performance
Location: Texas, 78401
State: Texas Government Spending