Construction of an Advanced Waste Water Treatment Plant (wwtp) With Capacity of Three Million Gallons PER DAY (MGD). Supporting Facilities Include Electric Service, Exterior Lighting, Water, Access Road, Paving, Walks, Information Systems, and Site Improvements
Contract Overview
Contract Amount: $25,126,158 ($25.1M)
Contractor: Joseph J Henderson & SON Inc
Awarding Agency: Department of Defense
Start Date: 2010-03-31
End Date: 2013-03-15
Contract Duration: 1,080 days
Daily Burn Rate: $23.3K/day
Official Description: CONSTRUCTION OF AN ADVANCED WASTE WATER TREATMENT PLANT (WWTP) WITH CAPACITY OF THREE MILLION GALLONS PER DAY (MGD). SUPPORTING FACILITIES INCLUDE ELECTRIC SERVICE, EXTERIOR LIGHTING, WATER, ACCESS ROAD, PAVING, WALKS, INFORMATION SYSTEMS, AND SITE IMPROVEMENTS.
Place of Performance
Location: Kansas, 66442
State: Kansas Government Spending