Replace Chiller 5 and Boilers 1, 2, and 3 AT the Womack Central Energy Plant. the Contractor Shall Provide ALL Labor, Materials, Equipment, and Supervision Necessary to Safely Complete the Activities Described in the SOW
Contract Overview
Contract Amount: $14,706,821 ($14.7M)
Contractor: SES Construction and Fuel Services LLC
Awarding Agency: Department of Defense
Start Date: 2025-09-24
End Date: 2027-10-08
Contract Duration: 744 days
Daily Burn Rate: $19.8K/day
Official Description: REPLACE CHILLER 5 AND BOILERS 1, 2, AND 3 AT THE WOMACK CENTRAL ENERGY PLANT. THE CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, EQUIPMENT, AND SUPERVISION NECESSARY TO SAFELY COMPLETE THE ACTIVITIES DESCRIBED IN THE SOW.
Place of Performance
Location: North Carolina, 28307