DoD's $28.5M Barracks Renovation Contract Awarded to Korte Construction Company Faces Scrutiny
Contract Overview
Contract Amount: $28,542,629 ($28.5M)
Contractor: Korte Construction Company
Awarding Agency: Department of Defense
Start Date: 2018-07-31
End Date: 2022-03-18
Contract Duration: 1,326 days
Daily Burn Rate: $21.5K/day
Competition Type: FULL AND OPEN COMPETITION
Number of Offers Received: 15
Pricing Type: FIRM FIXED PRICE
Sector: Construction
Official Description: IGF::OT::IGF P403 RECRUIT RECONDITIONING CENTER BARRACK RENOVATION
Place of Performance
Location: PARRIS ISLAND, BEAUFORT County, SOUTH CAROLINA, 29905
Plain-Language Summary
Department of Defense obligated $28.5 million to KORTE CONSTRUCTION COMPANY for work described as: IGF::OT::IGF P403 RECRUIT RECONDITIONING CENTER BARRACK RENOVATION Key points: 1. The contract awarded to Korte Construction Company for barracks renovation is for $28.5 million. 2. The contract was awarded under full and open competition. 3. The project duration was 1326 days, significantly longer than typical construction projects. 4. The sector is Commercial and Institutional Building Construction. 5. There is no indication of small business participation.
Value Assessment
Rating: questionable
The contract value of $28.5 million for barracks renovation appears high, especially considering the extended duration. Benchmarking against similar projects is difficult without more specific details on the scope of work, but the cost per day is substantial.
Cost Per Unit: N/A
Competition Analysis
Competition Level: full-and-open
The contract was awarded through full and open competition, suggesting a robust price discovery process. However, the extended duration and significant cost raise questions about whether the competitive process fully optimized value for taxpayers.
Taxpayer Impact: The substantial cost of this project, coupled with its long duration, suggests a potentially inefficient use of taxpayer funds if the value delivered does not align with the expenditure.
Public Impact
Military personnel may experience prolonged substandard living conditions due to the extended renovation timeline. Taxpayers are funding a significant expenditure for a project that has taken over three years to complete. The lack of small business involvement might represent a missed opportunity for economic development in the region.
Waste & Efficiency Indicators
Waste Risk Score: 50 / 10
Warning Flags
- Extended project duration
- High contract value for renovation
- No small business participation
Positive Signals
- Awarded through full and open competition
Sector Analysis
This contract falls within the Commercial and Institutional Building Construction sector. Spending in this sector can vary widely based on project scope, location, and economic conditions. The $28.5 million value is significant for a single renovation project.
Small Business Impact
The contract data indicates that small businesses were not involved in this award, either as prime contractors or potentially as subcontractors. This is a missed opportunity to support small business growth and economic diversification within the construction sector.
Oversight & Accountability
While awarded through full and open competition, the extended duration and significant cost warrant further oversight to ensure accountability and efficient use of funds. The contracting agency should monitor progress closely and address any delays or cost overruns.
Related Government Programs
- Commercial and Institutional Building Construction
- Department of Defense Contracting
- Department of the Navy Programs
Risk Flags
- Extended project duration
- High contract value
- Lack of small business participation
- Potential for cost overruns due to long timeline
Tags
commercial-and-institutional-building-co, department-of-defense, sc, definitive-contract, 10m-plus
Frequently Asked Questions
What is this federal contract paying for?
Department of Defense awarded $28.5 million to KORTE CONSTRUCTION COMPANY. IGF::OT::IGF P403 RECRUIT RECONDITIONING CENTER BARRACK RENOVATION
Who is the contractor on this award?
The obligated recipient is KORTE CONSTRUCTION COMPANY.
Which agency awarded this contract?
Awarding agency: Department of Defense (Department of the Navy).
What is the total obligated amount?
The obligated amount is $28.5 million.
What is the period of performance?
Start: 2018-07-31. End: 2022-03-18.
What specific factors contributed to the unusually long 1326-day duration for this barracks renovation project?
The extended duration of 1326 days (approximately 3.6 years) for this barracks renovation project is a significant concern. Potential contributing factors could include unforeseen site conditions, scope creep, contractor performance issues, funding delays, or complex logistical challenges inherent in military base construction. A detailed review of project milestones, change orders, and contractor reports would be necessary to pinpoint the exact causes.
How does the $28.5 million cost compare to similar barracks renovation projects of comparable scope and complexity?
Benchmarking the $28.5 million cost against similar barracks renovations is crucial for assessing value. Without detailed scope information, a direct comparison is difficult. However, the cost per square foot or per barracks unit needs to be evaluated against industry standards and other government contracts. If this project's cost significantly exceeds benchmarks, it suggests potential overpricing or inefficiencies that warrant investigation.
What measures were in place to ensure effective oversight and accountability given the long project timeline and substantial cost?
Effective oversight for a project of this magnitude and duration typically involves regular progress reviews, independent quality assurance checks, and stringent financial management. The Department of the Navy should have had contract officers and technical representatives actively monitoring the contractor's performance, adherence to schedule, and budget. Documentation of these oversight activities is essential to confirm accountability and justify the project's eventual cost and completion.
Industry Classification
NAICS: Construction › Nonresidential Building Construction › Commercial and Institutional Building Construction
Product/Service Code: CONSTRUCT OF STRUCTURES/FACILITIES › CONSTRUCTION OF BUILDINGS
Competition & Pricing
Extent Competed: FULL AND OPEN COMPETITION
Solicitation Procedures: TWO STEP
Solicitation ID: N4008516R5522
Offers Received: 15
Pricing Type: FIRM FIXED PRICE (J)
Evaluated Preference: NONE
Contractor Details
Address: 5700 OAKLAND AVE STE 275, SAINT LOUIS, MO, 63110
Business Categories: Category Business, Corporate Entity Not Tax Exempt, Not Designated a Small Business, Special Designations, Subchapter S Corporation, U.S.-Owned Business
Financial Breakdown
Contract Ceiling: $29,740,669
Exercised Options: $29,740,669
Current Obligation: $28,542,629
Subaward Activity
Number of Subawards: 129
Total Subaward Amount: $753,817,706
Contract Characteristics
Commercial Item: COMMERCIAL ITEM PROCEDURES NOT USED
Cost or Pricing Data: NO
Timeline
Start Date: 2018-07-31
Current End Date: 2022-03-18
Potential End Date: 2022-03-18 00:00:00
Last Modified: 2022-03-01
More Contracts from Korte Construction Company
- Disaster Resiliency Program (DRP) Phase 1 — $144.0M (Department of Defense)
- Gbsd CMF — $123.3M (Department of Defense)
- Disaster Resiliency Program (DRP) Phase 2 Creech AFB Nevada — $106.1M (Department of Defense)
- Design and Construction of the KC-46A Fuel Maintenance Hangar on the KC-46A Campus AT Tinker AFB, Oklahoma — $73.2M (Department of Defense)
- Aircraft Maintenance Hangar — $68.1M (Department of Defense)
Other Department of Defense Contracts
- Federal Contract — $51.3B (Humana Government Business Inc)
- Lrip LOT 12 Advance Acquisition Contract — $35.1B (Lockheed Martin Corporation)
- SSN 802 and 803 Long Lead Time Material — $34.7B (Electric Boat Corporation)
- 200204!008532!1700!AF600 !naval AIR Systems Command !N0001902C3002 !A!N! !N! !20011026!20120430!008016958!008016958!834951691!n!lockheed Martin Corporation !lockheed Blvd !fort Worth !tx!76108!27000!439!48!fort Worth !tarrant !texas !+000026000000!n!n!018981928201!ac15!rdte/Aircraft-Eng/Manuf Develop !a1a!airframes and Spares !2ama!jast/Jsf !336411!E! !3! ! ! ! ! !99990909!B! ! !A! !a!n!r!2!002!n!1a!a!n!z! ! !N!C!N! ! ! !a!a!a!a!000!a!c!n! ! ! !Y! !N00019!0001! — $34.2B (Lockheed Martin Corporation)
- KC-X Modernization Program — $32.0B (THE Boeing Company)