RED Bluff Pumping Plant and Fish Screen - Landfill Excavation & Canal, Siphon and Access Bridge - Arra Project NO. 16.020 TAS::14 0681::TAS
Contract Overview
Contract Amount: $24,663,539 ($24.7M)
Contractor: Thompson Builders Corp
Awarding Agency: Department of the Interior
Start Date: 2009-12-19
End Date: 2011-12-31
Contract Duration: 742 days
Daily Burn Rate: $33.2K/day
Official Description: RED BLUFF PUMPING PLANT AND FISH SCREEN - LANDFILL EXCAVATION & CANAL, SIPHON AND ACCESS BRIDGE - ARRA PROJECT NO. 16.020 TAS::14 0681::TAS
Place of Performance
Location: California, 96080