Correcting Entry: GSU Transformers, K19A and K20A Replacements, Grand Coulee Third Powerplant, Columbia Basin Project, Washington
Contract Overview
Contract Amount: $26,126,534 ($26.1M)
Contractor: Gardner Zemke CO
Awarding Agency: Department of the Interior
Start Date: 2009-10-02
End Date: 2012-11-06
Contract Duration: 1,131 days
Daily Burn Rate: $23.1K/day
Official Description: CORRECTING ENTRY: GSU TRANSFORMERS, K19A AND K20A REPLACEMENTS, GRAND COULEE THIRD POWERPLANT, COLUMBIA BASIN PROJECT, WASHINGTON