DHS Coast Guard awards $16.9M contract for Gulfport Station replacement to Tetra Tech Tesoro, Inc
Contract Overview
Contract Amount: $16,887,107 ($16.9M)
Contractor: Tetra Tech Tesoro, Inc.
Awarding Agency: Department of Homeland Security
Start Date: 2007-01-31
End Date: 2009-05-08
Contract Duration: 828 days
Daily Burn Rate: $20.4K/day
Competition Type: FULL AND OPEN COMPETITION
Number of Offers Received: 2
Pricing Type: OTHER (APPLIES TO AWARDS WHERE NONE OF THE ABOVE APPLY)
Sector: Construction
Official Description: DESIGN AND CONSTRUCTION SERVICES FOR THE REPLACEMENT OF STATION GULFPORT, GULFPORT, MS
Place of Performance
Location: GULFPORT, HARRISON County, MISSISSIPPI, 39501
Plain-Language Summary
Department of Homeland Security obligated $16.9 million to TETRA TECH TESORO, INC. for work described as: DESIGN AND CONSTRUCTION SERVICES FOR THE REPLACEMENT OF STATION GULFPORT, GULFPORT, MS Key points: 1. The contract value of $16.9M is for design and construction services. 2. Awarded under full and open competition, indicating a competitive bidding process. 3. The project aims to replace Station Gulfport, MS, a critical infrastructure need. 4. The contract duration was 828 days, suggesting a significant construction timeline.
Value Assessment
Rating: fair
The contract value of $16.9M appears reasonable for a significant infrastructure replacement project. Benchmarking against similar large-scale construction projects would provide a more definitive assessment.
Cost Per Unit: N/A
Competition Analysis
Competition Level: full-and-open
The contract was awarded through full and open competition, suggesting a robust price discovery process. This method typically leads to more competitive pricing as multiple bidders vie for the contract.
Taxpayer Impact: Taxpayer funds were utilized through a competitive process, aiming for value for money in the replacement of essential Coast Guard infrastructure.
Public Impact
Enhances U.S. Coast Guard operational capabilities in Gulfport, MS. Supports local economy through construction jobs and related services. Modernizes critical maritime infrastructure for improved safety and security.
Waste & Efficiency Indicators
Waste Risk Score: 50 / 10
Warning Flags
- Potential for cost overruns in large construction projects.
- Delays in project completion could impact operational readiness.
Positive Signals
- Awarded through full and open competition.
- Addresses critical infrastructure needs for the Coast Guard.
Sector Analysis
This contract falls under the construction sector, specifically for government facilities. Large-scale infrastructure projects like this often involve significant investment and require specialized expertise.
Small Business Impact
The data does not indicate if small businesses were involved as subcontractors. Further analysis would be needed to determine their participation.
Oversight & Accountability
Awarded as a delivery order, suggesting it was part of a larger indefinite-delivery/indefinite-quantity (IDIQ) contract or a similar framework. Oversight would focus on project execution and adherence to contract terms.
Related Government Programs
- Department of Homeland Security Contracting
- U.S. Coast Guard Programs
Risk Flags
- Potential for construction cost overruns.
- Risk of project delays impacting operational readiness.
- Dependency on contractor performance for successful completion.
- Need for robust oversight to ensure quality and adherence to specifications.
Tags
department-of-homeland-security, ms, delivery-order, 10m-plus
Frequently Asked Questions
What is this federal contract paying for?
Department of Homeland Security awarded $16.9 million to TETRA TECH TESORO, INC.. DESIGN AND CONSTRUCTION SERVICES FOR THE REPLACEMENT OF STATION GULFPORT, GULFPORT, MS
Who is the contractor on this award?
The obligated recipient is TETRA TECH TESORO, INC..
Which agency awarded this contract?
Awarding agency: Department of Homeland Security (U.S. Coast Guard).
What is the total obligated amount?
The obligated amount is $16.9 million.
What is the period of performance?
Start: 2007-01-31. End: 2009-05-08.
What was the final cost compared to the initial bid or estimated cost?
The provided data shows the awarded amount of $16,887,107.01. Without access to the initial bid proposals or the government's cost estimates, it's impossible to determine if the final cost represented a significant deviation. A comparison would reveal the efficiency of the bidding process and contractor's pricing accuracy.
Were there any significant delays or performance issues during the contract period?
The contract duration was 828 days (approximately 2.27 years). The data does not specify if the project was completed on time or if there were any performance issues. Post-award performance reviews and contract close-out documents would be necessary to assess any potential risks realized during execution.
How does the cost per square foot of the new station compare to similar government construction projects?
To assess the cost-effectiveness, the total square footage of the replacement station is needed. Once available, this metric could be compared to benchmarks for similar federal or state construction projects. This would provide insight into whether the $16.9M investment was competitive on a per-unit basis.
Competition & Pricing
Extent Competed: FULL AND OPEN COMPETITION
Offers Received: 2
Pricing Type: OTHER (APPLIES TO AWARDS WHERE NONE OF THE ABOVE APPLY) (3)
Evaluated Preference: NONE
Contractor Details
Parent Company: Tetra Tech, Inc. (UEI: 045224250)
Address: 520 S INDEPENDENCE BLVD #, VIRGINIA BEACH, VA, 23452
Business Categories: 8(a) Program Participant, Category Business, Self-Certified Small Disadvantaged Business, Small Business, Small Disadvantaged Business, Special Designations
Financial Breakdown
Contract Ceiling: $16,887,107
Exercised Options: $16,887,107
Current Obligation: $16,887,107
Contract Characteristics
Commercial Item: COMMERCIAL ITEM PROCEDURES NOT USED
Parent Contract
Parent Award PIID: DTCG4702D3EFK11
IDV Type: IDC
Timeline
Start Date: 2007-01-31
Current End Date: 2009-05-08
Potential End Date: 2009-05-08 00:00:00
Last Modified: 2016-12-29
More Contracts from Tetra Tech Tesoro, Inc.
- Construction/Additions Supreme Allied Commander Transformation Headquarters Building — $33.7M (Department of Defense)
- Base Year — $30.3M (Department of Defense)
- Base Year — $26.0M (Department of Defense)
- P527 Design Build Perimeter Security and Main Entrance Improvements — $23.3M (Department of Defense)
- Construction of Building 61 and Basement Renovation of Buildign 19, Department of Homeland Security, Nebraska Avenue Complex (NAC), Washington, DC — $20.9M (Department of Homeland Security)
Other Department of Homeland Security Contracts
- THE United States Coast Guard HAS a Requirement to Procure UP to Twenty-Six (26) Fast Response Cutters (frcs) on a Firm Fixed Price (FFP) Basis With an Economic Price Adjustment (EPA). Phase II of the FRC Program Will Complete the Fleet for a Total of 58 Cutters — $2.1B (Bollinger Shipyards Lockport, L.L.C.)
- Design and Construct NEW Vertical Barrier and Power Distribution, Lighting, Cameras, Equipment Shelters and Linear Ground Detection System (lgds) in Hildago County, NM — $1.8B (Fisher Sand & Gravel CO)
- Production&delivery of National Security Cutter (NSC) 6 — $1.7B (Huntington Ingalls Incorporated)
- YUM-2 Vertical Border and Waterborne Barrier Construction — $1.7B (Fisher Sand & Gravel CO)
- Construct Vertical Border Barrier — $1.6B (Fisher Sand & Gravel CO)