GSA Awards $21.6M for FDA Road and Bridge Construction to Total Engineering, Inc

Contract Overview

Contract Amount: $21,598,123 ($21.6M)

Contractor: Total Engineering, Inc.

Awarding Agency: General Services Administration

Start Date: 2008-07-31

End Date: 2010-10-30

Contract Duration: 821 days

Daily Burn Rate: $26.3K/day

Competition Type: FULL AND OPEN COMPETITION

Number of Offers Received: 3

Pricing Type: FIRM FIXED PRICE

Sector: Construction

Official Description: ROAD AND BRIDGE CONSTRUCTION, FDA AT WHITE OAK, SILVER SPRING, MARYLAND

Place of Performance

Location: SILVER SPRING, MONTGOMERY County, MARYLAND, 20903

State: Maryland Government Spending

Plain-Language Summary

General Services Administration obligated $21.6 million to TOTAL ENGINEERING, INC. for work described as: ROAD AND BRIDGE CONSTRUCTION, FDA AT WHITE OAK, SILVER SPRING, MARYLAND Key points: 1. The contract value of $21.6 million is for highway, street, and bridge construction. 2. Total Engineering, Inc. secured the contract under full and open competition. 3. The project duration was 821 days, indicating a significant construction timeline. 4. The absence of small business participation is noted.

Value Assessment

Rating: fair

The contract value of $21.6 million for road and bridge construction appears within a reasonable range for a project of this scope and duration. Benchmarking against similar federal construction contracts would provide a more precise assessment.

Cost Per Unit: N/A

Competition Analysis

Competition Level: full-and-open

The contract was awarded using full and open competition, which generally promotes competitive pricing and allows for a broad range of contractors to bid. This method is expected to yield fair market prices.

Taxpayer Impact: The use of full and open competition suggests that taxpayer funds were likely used efficiently by fostering a competitive bidding environment.

Public Impact

Improved infrastructure at the FDA's White Oak campus, enhancing operational efficiency. Potential for increased traffic flow and accessibility around the facility. Creation of construction-related jobs during the project's execution.

Waste & Efficiency Indicators

Waste Risk Score: 50 / 10

Warning Flags

  • No small business participation.
  • Long project duration (821 days).

Positive Signals

  • Full and open competition.
  • Firm fixed price contract.

Sector Analysis

This contract falls within the construction sector, specifically highway, street, and bridge construction. Federal spending in this area is crucial for maintaining and upgrading national infrastructure, with project costs varying significantly based on scale and complexity.

Small Business Impact

The contract data indicates that no small businesses were involved in this award. This suggests a lack of opportunity for small business participation in this specific project, which could be a missed opportunity for economic development.

Oversight & Accountability

The General Services Administration (GSA), through its Public Buildings Service, managed this procurement. Oversight would typically involve monitoring project progress, adherence to contract terms, and quality of work to ensure taxpayer value.

Related Government Programs

  • Highway, Street, and Bridge Construction
  • General Services Administration Contracting
  • Public Buildings Service Programs

Risk Flags

  • Lack of small business participation.
  • Long contract duration may indicate potential for cost overruns or delays.
  • No clear indication of value engineering or cost-saving measures implemented.

Tags

highway-street-and-bridge-construction, general-services-administration, md, dca, 10m-plus

Frequently Asked Questions

What is this federal contract paying for?

General Services Administration awarded $21.6 million to TOTAL ENGINEERING, INC.. ROAD AND BRIDGE CONSTRUCTION, FDA AT WHITE OAK, SILVER SPRING, MARYLAND

Who is the contractor on this award?

The obligated recipient is TOTAL ENGINEERING, INC..

Which agency awarded this contract?

Awarding agency: General Services Administration (Public Buildings Service).

What is the total obligated amount?

The obligated amount is $21.6 million.

What is the period of performance?

Start: 2008-07-31. End: 2010-10-30.

What was the primary driver for the specific scope of road and bridge construction at the FDA White Oak campus?

The primary driver for the road and bridge construction at the FDA White Oak campus was likely to support the expansion, modernization, or improved accessibility of the facility. This could include accommodating increased traffic, enhancing safety, or integrating new infrastructure with existing or planned buildings.

Were there any specific performance issues or challenges encountered during the 821-day contract period?

The provided data does not detail specific performance issues or challenges encountered during the 821-day contract period. A thorough review of contract performance reports, project close-out documents, and any change order logs would be necessary to identify any such issues and their resolution.

How does the final cost compare to the initial bid or estimated cost for this project?

The data provided does not include the initial bid or estimated cost, only the awarded value of $21,598,122.51. To assess cost-effectiveness, a comparison with the original bid submitted by Total Engineering, Inc. and any independent government cost estimates would be required.

Industry Classification

NAICS: ConstructionHighway, Street, and Bridge ConstructionHighway, Street, and Bridge Construction

Product/Service Code: CONSTRUCT OF STRUCTURES/FACILITIESCONSTRUCT NONBUILDING FACILITIES

Competition & Pricing

Extent Competed: FULL AND OPEN COMPETITION

Solicitation Procedures: NEGOTIATED PROPOSAL/QUOTE

Solicitation ID: GS-11P-08-MK-C-0005

Offers Received: 3

Pricing Type: FIRM FIXED PRICE (J)

Evaluated Preference: NONE

Contractor Details

Address: 8240 PROFESSIONAL PLACE STE 205, LANDOVER, MD, 04

Business Categories: Category Business, Corporate Entity Not Tax Exempt, Hispanic American Owned Business, Minority Owned Business, Self-Certified Small Disadvantaged Business, Small Business, Special Designations, Subchapter S Corporation, U.S.-Owned Business

Financial Breakdown

Contract Ceiling: $21,598,123

Exercised Options: $21,598,123

Current Obligation: $21,598,123

Timeline

Start Date: 2008-07-31

Current End Date: 2010-10-30

Potential End Date: 2010-10-30 00:00:00

Last Modified: 2012-02-09

Other General Services Administration Contracts

View all General Services Administration contracts →

Explore Related Government Spending