Hanford Mission Essential Services Contract- Reliability Task Order-012- Project L-888, Eastern Plateau Fire Station
Contract Overview
Contract Amount: $34,949,406 ($34.9M)
Contractor: Hanford Mission Integration Solutions, LLC
Awarding Agency: Department of Energy
Start Date: 2025-08-15
End Date: 2028-08-31
Contract Duration: 1,112 days
Daily Burn Rate: $31.4K/day
Official Description: HANFORD MISSION ESSENTIAL SERVICES CONTRACT- RELIABILITY TASK ORDER-012- PROJECT L-888, EASTERN PLATEAU FIRE STATION.
Place of Performance
Location: Washington, 99354