THE Contractor Shall Provide ALL Tools, Equipment, Materials, Labor, Supervision, Personnel, and Shall DO ALL Things Necessary That Will Result in the Completion of the Ehrm Infrastructure Upgrades Construction Project

Contract Overview

Contract Amount: $13,371,231 ($13.4M)

Contractor: Hurley JV, LLP

Awarding Agency: Department of Veterans Affairs

Start Date: 2024-05-16

End Date: 2025-09-08

Contract Duration: 480 days

Daily Burn Rate: $27.9K/day

Official Description: THE CONTRACTOR SHALL PROVIDE ALL TOOLS, EQUIPMENT, MATERIALS, LABOR, SUPERVISION, PERSONNEL, AND SHALL DO ALL THINGS NECESSARY THAT WILL RESULT IN THE COMPLETION OF THE EHRM INFRASTRUCTURE UPGRADES CONSTRUCTION PROJECT.

Place of Performance

Location: Wyoming, 82801