VA Awards $5.1M Contract for EHRM Data Center Construction at Kansas City VAMC
Contract Overview
Contract Amount: $5,120,204 ($5.1M)
Contractor: Falcon JV, LLC
Awarding Agency: Department of Veterans Affairs
Start Date: 2023-10-13
End Date: 2026-02-05
Contract Duration: 846 days
Daily Burn Rate: $6.1K/day
Competition Type: FULL AND OPEN COMPETITION AFTER EXCLUSION OF SOURCES
Number of Offers Received: 3
Pricing Type: FIRM FIXED PRICE
Sector: Construction
Official Description: CONSTRUCTION CONTRACT TO UPDATE EHRM DATA IN DATA CENTER AT KANSAS CITY MO VAMC
Place of Performance
Location: KANSAS CITY, CLAY County, MISSOURI, 64116
State: Missouri Government Spending
Plain-Language Summary
Department of Veterans Affairs obligated $5.1 million to FALCON JV, LLC for work described as: CONSTRUCTION CONTRACT TO UPDATE EHRM DATA IN DATA CENTER AT KANSAS CITY MO VAMC Key points: 1. Contract awarded to Falcon JV, LLC for $5.1M. 2. Project involves updating EHRM data in a data center. 3. Competition was full and open after exclusion of sources. 4. The sector is Commercial and Institutional Building Construction.
Value Assessment
Rating: fair
The contract value of $5.1M for construction services appears within a reasonable range for data center upgrades. Benchmarking against similar VA or other federal data center construction projects would provide a more precise assessment of value.
Cost Per Unit: N/A
Competition Analysis
Competition Level: full-and-open
The contract was awarded under full and open competition after exclusion of sources, indicating an attempt to broaden the bidder pool. This method generally supports competitive pricing, though the specific impact depends on the number and capability of bidders.
Taxpayer Impact: The $5.1M expenditure supports critical infrastructure upgrades for the VA's Electronic Health Record Modernization (EHRM) program, aiming for improved data management and system efficiency.
Public Impact
Enhances the reliability and security of veteran health data. Supports the broader Electronic Health Record Modernization (EHRM) initiative. Invests in critical IT infrastructure at a major VA facility. Potential for improved healthcare delivery through better data access.
Waste & Efficiency Indicators
Waste Risk Score: 50 / 10
Warning Flags
- Limited information on specific construction scope and potential cost overruns.
- Exclusion of sources in the competition phase warrants further review.
- Long contract duration (846 days) increases risk of scope creep or market changes.
Positive Signals
- Focus on critical EHRM data infrastructure.
- Utilizes a full and open competition strategy.
- Fixed-price contract type can control costs if scope is well-defined.
Sector Analysis
The construction sector, particularly for specialized facilities like data centers, requires significant investment. Benchmarks for similar government data center construction projects vary widely based on size, complexity, and location.
Small Business Impact
The contract was not awarded to a small business. Further analysis would be needed to determine if small business participation was sought or achieved through subcontracting.
Oversight & Accountability
Oversight will be crucial to ensure the project stays within budget and schedule, given the complexity of data center construction and the long duration. The VA's contracting and project management offices will be responsible for monitoring progress and performance.
Related Government Programs
- Commercial and Institutional Building Construction
- Department of Veterans Affairs Contracting
- Department of Veterans Affairs Programs
Risk Flags
- Potential for cost overruns due to construction complexity.
- Risk of schedule delays impacting EHRM modernization timeline.
- Adequacy of competition despite 'exclusion of sources' method.
- Long contract duration increasing exposure to market fluctuations.
- Ensuring long-term technological relevance of the upgrades.
Tags
commercial-and-institutional-building-co, department-of-veterans-affairs, mo, definitive-contract, 1m-plus
Frequently Asked Questions
What is this federal contract paying for?
Department of Veterans Affairs awarded $5.1 million to FALCON JV, LLC. CONSTRUCTION CONTRACT TO UPDATE EHRM DATA IN DATA CENTER AT KANSAS CITY MO VAMC
Who is the contractor on this award?
The obligated recipient is FALCON JV, LLC.
Which agency awarded this contract?
Awarding agency: Department of Veterans Affairs (Department of Veterans Affairs).
What is the total obligated amount?
The obligated amount is $5.1 million.
What is the period of performance?
Start: 2023-10-13. End: 2026-02-05.
What specific technological upgrades are included in the EHRM data center update, and how do they align with future VA IT needs?
The provided data lacks specifics on the technological upgrades. A detailed review of the contract's SOW would be necessary to understand the scope, such as server capacity expansion, cooling system enhancements, or network infrastructure modernization. Understanding these details is crucial to assess if the upgrades are future-proof and align with the VA's long-term IT strategy for EHRM.
What was the rationale for excluding specific sources prior to the full and open competition, and did this exclusion impact the final contract price?
The rationale for excluding sources before the 'full and open competition after exclusion of sources' is not detailed in the provided data. This specific procurement method suggests that certain potential bidders were initially disqualified or not solicited. Understanding the reasons for exclusion is important to ensure fairness and to assess if it limited competitive pressure, potentially affecting the final price achieved.
How will the VA measure the effectiveness of this data center upgrade in improving EHRM performance and data accessibility for healthcare providers?
Effectiveness will likely be measured through key performance indicators (KPIs) related to system uptime, data retrieval speeds, system latency, and user satisfaction surveys from healthcare providers. The contract should ideally outline specific, measurable, achievable, relevant, and time-bound (SMART) goals for these metrics post-upgrade to ensure the investment translates into tangible improvements in healthcare delivery.
Industry Classification
NAICS: Construction › Nonresidential Building Construction › Commercial and Institutional Building Construction
Product/Service Code: CONSTRUCT OF STRUCTURES/FACILITIES › CONSTRUCTION OF BUILDINGS
Competition & Pricing
Extent Competed: FULL AND OPEN COMPETITION AFTER EXCLUSION OF SOURCES
Solicitation Procedures: SEALED BID
Solicitation ID: 36C77623B0065
Offers Received: 3
Pricing Type: FIRM FIXED PRICE (J)
Evaluated Preference: NONE
Contractor Details
Address: 130 E 13TH AVE, KANSAS CITY, MO, 64116
Business Categories: Category Business, Limited Liability Corporation, Partnership or Limited Liability Partnership, Self-Certified Small Disadvantaged Business, Service Disabled Veteran Owned Business, Small Business, Special Designations, U.S.-Owned Business, Veteran Owned Business
Financial Breakdown
Contract Ceiling: $5,120,204
Exercised Options: $5,120,204
Current Obligation: $5,120,204
Contract Characteristics
Commercial Item: COMMERCIAL PRODUCTS/SERVICES PROCEDURES NOT USED
Cost or Pricing Data: NO
Timeline
Start Date: 2023-10-13
Current End Date: 2026-02-05
Potential End Date: 2026-02-05 00:00:00
Last Modified: 2026-03-17
Other Department of Veterans Affairs Contracts
- CCN Region 3 Express Report — $5.2B (Optum Public Sector Solutions, Inc.)
- Express Report for FY22 Region 2 — $5.1B (Optum Public Sector Solutions, Inc.)
- Fiscal Year 2022 Express Report for Region 1 — $4.2B (Optum Public Sector Solutions, Inc.)
- Express Report for the Patient Centered Community Care (PC3) Contract — $3.3B (Triwest Healthcare Alliance Corp)
- CCN Region Three FY21 Express Report — $3.1B (Optum Public Sector Solutions, Inc.)