This Project Will Replace Existing Stehekin Wastewater Treatment Plant (wwtp) With a Modern Facility. Project Scope Includes Demolition and Removal of Existing Package Skid and Tanks, Rehabilitation and Upgrade of the Building, and Installation of N

Contract Overview

Contract Amount: $11,587,350 ($11.6M)

Contractor: HB Hansen Construction, Inc.

Awarding Agency: Department of the Interior

Start Date: 2023-09-21

End Date: 2026-06-01

Contract Duration: 984 days

Daily Burn Rate: $11.8K/day

Official Description: THIS PROJECT WILL REPLACE EXISTING STEHEKIN WASTEWATER TREATMENT PLANT (WWTP) WITH A MODERN FACILITY. PROJECT SCOPE INCLUDES DEMOLITION AND REMOVAL OF EXISTING PACKAGE SKID AND TANKS, REHABILITATION AND UPGRADE OF THE BUILDING, AND INSTALLATION OF N

Place of Performance

Location: Washington, 98852

State: Washington Government Spending