OAC Action Construction Corp. awarded $1.99M for Wheeler Maintenance Shop Facility construction in Alabama
Contract Overview
Contract Amount: $1,992,125 ($2.0M)
Contractor: OAC Action Construction Corp.
Awarding Agency: Department of the Interior
Start Date: 2025-04-02
End Date: 2026-12-31
Contract Duration: 638 days
Daily Burn Rate: $3.1K/day
Competition Type: FULL AND OPEN COMPETITION AFTER EXCLUSION OF SOURCES
Number of Offers Received: 5
Pricing Type: FIRM FIXED PRICE
Sector: Construction
Official Description: CONSTRUCTION SERVICES WHEELER MAINTENANCE SHOP FACILITY
Place of Performance
Location: DECATUR, MORGAN County, ALABAMA, 35603
State: Alabama Government Spending
Plain-Language Summary
Department of the Interior obligated $2.0 million to OAC ACTION CONSTRUCTION CORP. for work described as: CONSTRUCTION SERVICES WHEELER MAINTENANCE SHOP FACILITY Key points: 1. Contract awarded via full and open competition, suggesting a competitive bidding process. 2. The contract is a firm fixed-price type, which shifts cost risk to the contractor. 3. The duration of 638 days indicates a significant construction project. 4. The project is located in Alabama, potentially benefiting the local construction workforce. 5. The contract is a delivery order, implying it's part of a larger indefinite-delivery/indefinite-quantity (IDIQ) contract or a similar framework.
Value Assessment
Rating: good
The contract value of $1.99 million for a maintenance shop facility appears reasonable given the project scope and duration. Without specific details on the facility's size and complexity, a direct comparison is challenging. However, the firm fixed-price structure suggests that the government has secured a defined cost, which is a positive indicator for value. Further analysis would require benchmarking against similar construction projects of comparable scale and complexity.
Cost Per Unit: N/A
Competition Analysis
Competition Level: full-and-open
This contract was awarded under 'full and open competition after exclusion of sources,' indicating that multiple bidders were likely considered. The presence of 5 bids suggests a healthy level of competition for this project. A competitive process generally leads to better price discovery and potentially more favorable terms for the government.
Taxpayer Impact: The competitive nature of this award is beneficial for taxpayers, as it likely resulted in a more cost-effective solution compared to a sole-source or limited competition scenario.
Public Impact
The U.S. Fish and Wildlife Service will benefit from the new maintenance shop facility. The construction services will result in a new facility to support maintenance operations. The project's geographic impact is concentrated in Alabama. The construction activities will likely involve and benefit the local Alabama workforce.
Waste & Efficiency Indicators
Waste Risk Score: 50 / 10
Warning Flags
- Potential for cost overruns if unforeseen site conditions arise, despite the fixed-price nature.
- Delays in construction could impact the operational readiness of the maintenance facility.
- Ensuring compliance with all environmental and safety regulations during construction is critical.
Positive Signals
- Firm fixed-price contract mitigates budget uncertainty for the government.
- Competitive bidding process likely secured a fair market price.
- The project addresses a clear need for facility improvement or expansion.
Sector Analysis
This contract falls within the Commercial and Institutional Building Construction sector. This sector is characterized by a wide range of projects, from small renovations to large-scale new builds. The market size for construction services is substantial, driven by both public and private sector demand. This specific contract represents a modest investment within the broader construction industry, focused on a specialized facility for a government agency.
Small Business Impact
The data indicates that this contract was not set aside for small businesses, nor does it explicitly mention subcontracting goals for small businesses. Therefore, the direct impact on the small business ecosystem is likely minimal unless the prime contractor voluntarily engages small businesses for subcontracting opportunities. Further investigation into the contractor's subcontracting plan would be necessary to assess any indirect benefits.
Oversight & Accountability
Oversight for this contract will likely be managed by the U.S. Fish and Wildlife Service contracting officer and project managers. Accountability measures are inherent in the firm fixed-price contract, requiring the contractor to deliver the specified facility within the agreed-upon cost and timeline. Transparency is generally maintained through contract award databases, though detailed project progress reports may not always be publicly accessible.
Related Government Programs
- Federal Building Construction
- Government Facilities Maintenance
- Public Works Projects
- Department of the Interior Construction Contracts
Risk Flags
- Potential for schedule delays
- Quality control during construction
- Environmental compliance
Tags
construction, department-of-the-interior, u-s-fish-and-wildlife-service, alabama, firm-fixed-price, delivery-order, full-and-open-competition, commercial-and-institutional-building-construction, maintenance-facility, medium-value
Frequently Asked Questions
What is this federal contract paying for?
Department of the Interior awarded $2.0 million to OAC ACTION CONSTRUCTION CORP.. CONSTRUCTION SERVICES WHEELER MAINTENANCE SHOP FACILITY
Who is the contractor on this award?
The obligated recipient is OAC ACTION CONSTRUCTION CORP..
Which agency awarded this contract?
Awarding agency: Department of the Interior (U.S. Fish and Wildlife Service).
What is the total obligated amount?
The obligated amount is $2.0 million.
What is the period of performance?
Start: 2025-04-02. End: 2026-12-31.
What is the specific purpose and scope of the Wheeler Maintenance Shop Facility?
The provided data indicates the contract is for 'CONSTRUCTION SERVICES WHEELER MAINTENANCE SHOP FACILITY.' While the exact specifications are not detailed, the name suggests the facility will serve as a location for the maintenance and repair of equipment or vehicles used by the U.S. Fish and Wildlife Service. This could include administrative buildings, workshops, storage areas, and associated infrastructure necessary for operational support. The firm fixed-price nature of the contract implies a well-defined scope of work was established prior to bidding to ensure cost certainty for the government.
How does the awarded price of $1.99 million compare to similar construction projects?
Benchmarking the $1.99 million award requires more specific details about the facility's size (square footage), complexity, and specific construction elements (e.g., specialized equipment installation, environmental controls). However, for a maintenance shop facility of significant size and duration (638 days), this figure appears within a reasonable range for construction projects. Without comparable data points for similar government facilities in Alabama or the surrounding region, a precise value-for-money assessment is difficult. The competitive bidding process, however, suggests the price reflects market conditions.
What are the primary risks associated with this firm fixed-price construction contract?
The primary risks for the government in a firm fixed-price contract are minimal regarding cost overruns, as the contractor assumes most of that risk. However, risks can shift to performance and schedule. The contractor might be incentivized to cut corners on quality to maintain profitability, necessitating robust government oversight and quality assurance. Delays are also a risk, as the contractor may face challenges meeting the schedule, potentially impacting the agency's operations. Unforeseen site conditions, though often addressed in contract clauses, can also lead to disputes or change orders, even in fixed-price contracts.
What is the track record of OAC ACTION CONSTRUCTION CORP. with federal contracts?
Information regarding OAC ACTION CONSTRUCTION CORP.'s specific track record with federal contracts is not provided in the data. A comprehensive assessment would require reviewing their past performance on similar government projects, including contract history, past performance evaluations, and any history of disputes or contract terminations. Federal procurement databases (like SAM.gov or FPDS) would typically contain this information, allowing for an analysis of their reliability, quality of work, and adherence to schedules and budgets on previous federal awards.
How does the competition level (5 bidders) impact the value for taxpayers?
A competition level of 5 bidders is generally considered healthy and indicates that the contract was adequately publicized and attracted significant interest from qualified contractors. This level of competition typically drives down prices as contractors vie for the award, leading to a more cost-effective outcome for taxpayers. It also increases the likelihood that the government receives a proposal that meets its technical requirements at a competitive price. A higher number of bidders usually correlates with better price discovery and a stronger position for the government in negotiations.
What are the potential workforce implications of this construction project in Alabama?
This construction project is likely to have positive implications for the local workforce in Alabama. Construction projects of this scale typically require a variety of skilled trades, including carpenters, electricians, plumbers, heavy equipment operators, and general laborers. Awarding the contract to OAC ACTION CONSTRUCTION CORP. suggests that the company will likely hire locally or draw from the existing regional labor pool to staff the project. This can lead to job creation, increased economic activity, and skill development within the local community for the duration of the project.
Industry Classification
NAICS: Construction › Nonresidential Building Construction › Commercial and Institutional Building Construction
Product/Service Code: CONSTRUCT OF STRUCTURES/FACILITIES › CONSTRUCTION OF BUILDINGS
Competition & Pricing
Extent Competed: FULL AND OPEN COMPETITION AFTER EXCLUSION OF SOURCES
Solicitation Procedures: SUBJECT TO MULTIPLE AWARD FAIR OPPORTUNITY
Solicitation ID: 0040663341
Offers Received: 5
Pricing Type: FIRM FIXED PRICE (J)
Evaluated Preference: NONE
Contractor Details
Address: 11980 SW 144TH CT STE 101, MIAMI, FL, 33186
Business Categories: Category Business, Corporate Entity Not Tax Exempt, DoT Certified Disadvantaged Business Enterprise, Hispanic American Owned Business, Minority Owned Business, Self-Certified Small Disadvantaged Business, Small Business, Special Designations, Subchapter S Corporation, U.S.-Owned Business
Financial Breakdown
Contract Ceiling: $1,992,125
Exercised Options: $1,992,125
Current Obligation: $1,992,125
Actual Outlays: $502,439
Contract Characteristics
Commercial Item: COMMERCIAL PRODUCTS/SERVICES PROCEDURES NOT USED
Cost or Pricing Data: NO
Parent Contract
Parent Award PIID: 140F0822D0085
IDV Type: IDC
Timeline
Start Date: 2025-04-02
Current End Date: 2026-12-31
Potential End Date: 2026-12-31 00:00:00
Last Modified: 2026-03-19
More Contracts from OAC Action Construction Corp.
- Multi-Purpose Building AT Florida Panther National Wildlife Refuge — $4.6M (Department of the Interior)
- Design and Build for Phase 2 Renovations of the Hurlburt Field AIR Park — $2.0M (Department of Defense)
Other Department of the Interior Contracts
- Department of Health and Human Services, Administration of Children and Families, Office of Refugee Resettlement's Legal Services for Unaccompanied Children — $832.4M (Acacia Center for Justice)
- Military Family Life Counseling Program Igf::ot::igf — $638.8M (MHN Government Services LLC)
- Military Family Life Counseling Program — $637.0M (Magellan Healthcare Inc)
- Grants Program Solutions and Information Technology Support Services — $446.3M (Guidehouse Digital LLC)
- THE Purpose of This Requirement for Grants Program Solutions and IT Support Services IS to Provide Efficient and Effective Grant, Financial, and Contract Management Services, IT Solutions, and Support to the Grantsolutions and ITS Partners — $403.1M (Guidehouse Inc.)