WBV 14C.2, West Bank and Vicinity, Westwego to Harvey Canal Hurricane Storm Damage Risk Reduction System, NEW Westwego PS to Orleans Village Phase 2, First Lift Levee and Floodwalls AT Westminster PS, Wbv-14c.2

Contract Overview

Contract Amount: $32,521,705 ($32.5M)

Contractor: Phylway Construction, L.L.C.

Awarding Agency: Department of Defense

Start Date: 2010-06-14

End Date: 2014-02-20

Contract Duration: 1,347 days

Daily Burn Rate: $24.1K/day

Official Description: WBV 14C.2, WEST BANK AND VICINITY, WESTWEGO TO HARVEY CANAL HURRICANE STORM DAMAGE RISK REDUCTION SYSTEM, NEW WESTWEGO PS TO ORLEANS VILLAGE PHASE 2, FIRST LIFT LEVEE AND FLOODWALLS AT WESTMINSTER PS, WBV-14C.2

Place of Performance

Location: Louisiana, 70058

State: Louisiana Government Spending