ER - Herc Contract - Temporary Pump Stations, NEW Orleans, LA
Contract Overview
Contract Amount: $26,808,322 ($26.8M)
Contractor: Weston Solutions Inc
Awarding Agency: Department of Defense
Start Date: 2007-04-09
End Date: 2009-01-30
Contract Duration: 662 days
Daily Burn Rate: $40.5K/day
Official Description: ER - HERC CONTRACT - TEMPORARY PUMP STATIONS, NEW ORLEANS, LA
Place of Performance
Location: Louisiana, 70130