WBV 15A.2, West Bank & Vicinity, Lake Cataouatche Levee Enlargement, Pump Station to Segnette State Park, Phase 2
Contract Overview
Contract Amount: $41,872,685 ($41.9M)
Contractor: Phylway Construction, L.L.C.
Awarding Agency: Department of Defense
Start Date: 2010-02-02
End Date: 2011-09-05
Contract Duration: 580 days
Daily Burn Rate: $72.2K/day
Official Description: WBV 15A.2, WEST BANK & VICINITY, LAKE CATAOUATCHE LEVEE ENLARGEMENT, PUMP STATION TO SEGNETTE STATE PARK, PHASE 2
Place of Performance
Location: Louisiana, 70037