Delivery Order on a Requirements Contract for 13 Improved Ribbon Bridge (IRB) Interior Bays, 6 Ramp Bays, and Fielding AT FT. Polk
Contract Overview
Contract Amount: $18,682,045 ($18.7M)
Contractor: General Dynamics European Land Systems-Bridge Systems Gmbh
Awarding Agency: Department of Defense
Start Date: 2009-03-19
End Date: 2013-05-13
Contract Duration: 1,516 days
Daily Burn Rate: $12.3K/day
Official Description: DELIVERY ORDER ON A REQUIREMENTS CONTRACT FOR 13 IMPROVED RIBBON BRIDGE (IRB) INTERIOR BAYS, 6 RAMP BAYS, AND FIELDING AT FT. POLK