DoD Awards $16.9M for Camp Lejeune Construction to Virtexco Corp Under Full and Open Competition
Contract Overview
Contract Amount: $16,894,195 ($16.9M)
Contractor: Virtexco Corp
Awarding Agency: Department of Defense
Start Date: 2009-09-23
End Date: 2013-03-15
Contract Duration: 1,269 days
Daily Burn Rate: $13.3K/day
Competition Type: FULL AND OPEN COMPETITION
Number of Offers Received: 4
Pricing Type: FIRM FIXED PRICE
Sector: Construction
Official Description: AWARD OF P1330 AND P1378 IN CAMP LEJEUNE, NC
Place of Performance
Location: CAMP LEJEUNE, ONSLOW County, NORTH CAROLINA, 28547
Plain-Language Summary
Department of Defense obligated $16.9 million to VIRTEXCO CORP for work described as: AWARD OF P1330 AND P1378 IN CAMP LEJEUNE, NC Key points: 1. The contract awarded to Virtexco Corp for construction services at Camp Lejeune represents a significant investment in military infrastructure. 2. Full and open competition was utilized, suggesting a robust process for selecting the contractor and potentially achieving competitive pricing. 3. The project duration of 1269 days indicates a substantial and complex construction undertaking. 4. The North Carolina location places the spending within a specific regional economic context for construction services.
Value Assessment
Rating: fair
The award amount of $16.9 million for construction services needs to be benchmarked against similar projects in the region and for similar scope to assess value. Without specific details on the scope of work for P1330 and P1378, a precise pricing assessment is difficult.
Cost Per Unit: N/A
Competition Analysis
Competition Level: full-and-open
The contract was awarded under full and open competition, which typically allows for the widest possible range of bidders and promotes price discovery. This method is generally expected to yield competitive pricing for the government.
Taxpayer Impact: The use of full and open competition aims to ensure taxpayer funds are used efficiently by securing the best value through a competitive bidding process.
Public Impact
Local construction firms and suppliers in North Carolina may have benefited from subcontracting opportunities. The completed construction projects will enhance the operational capabilities and living conditions at Camp Lejeune. This award contributes to the broader economic activity within the construction sector in the region.
Waste & Efficiency Indicators
Waste Risk Score: 50 / 10
Warning Flags
- Lack of specific scope of work details for P1330 and P1378.
- No clear indication of small business participation.
- Limited data to assess cost-effectiveness beyond the award amount.
Positive Signals
- Awarded under full and open competition.
- Significant investment in critical military infrastructure.
- Firm fixed price contract type provides cost certainty.
Sector Analysis
The contract falls under the Commercial and Institutional Building Construction sector, specifically for the Department of the Navy. Spending benchmarks for similar military construction projects would be relevant for a deeper value assessment.
Small Business Impact
The provided data indicates that the contract was not awarded to a small business (ss: false, sb: false). Further analysis would be needed to determine if small business subcontracting goals were established or met.
Oversight & Accountability
The Department of the Navy, as the awarding agency, is responsible for oversight. The firm fixed price contract type offers some cost control, but monitoring project execution and quality is crucial for accountability.
Related Government Programs
- Commercial and Institutional Building Construction
- Department of Defense Contracting
- Department of the Navy Programs
Risk Flags
- Lack of detailed scope of work.
- No small business participation noted.
- Long project duration increases risk of cost escalation.
- Limited data for comprehensive value assessment.
Tags
commercial-and-institutional-building-co, department-of-defense, nc, delivery-order, 10m-plus
Frequently Asked Questions
What is this federal contract paying for?
Department of Defense awarded $16.9 million to VIRTEXCO CORP. AWARD OF P1330 AND P1378 IN CAMP LEJEUNE, NC
Who is the contractor on this award?
The obligated recipient is VIRTEXCO CORP.
Which agency awarded this contract?
Awarding agency: Department of Defense (Department of the Navy).
What is the total obligated amount?
The obligated amount is $16.9 million.
What is the period of performance?
Start: 2009-09-23. End: 2013-03-15.
What was the specific scope of work for contract numbers P1330 and P1378, and how did Virtexco Corp's bid compare to other proposals?
The specific scope of work for P1330 and P1378 is not detailed in the provided data. Understanding the exact nature of the construction projects (e.g., new buildings, renovations, specific facilities) is crucial for evaluating the $16.9 million award. A comparison of Virtexco Corp's bid against other proposals would reveal the extent of price discovery achieved through the full and open competition process.
What are the potential risks associated with a 1269-day construction project at a military installation, and how were these mitigated?
Risks for a long-duration construction project at a military base can include cost overruns due to inflation or unforeseen site conditions, schedule delays from weather or logistical challenges, and potential impacts on base operations. Mitigation strategies might involve robust contingency planning, detailed site investigations, phased construction approaches, and strong contract management by the Navy to ensure adherence to timelines and budgets.
How effectively does this $16.9 million award contribute to the long-term infrastructure needs and operational readiness at Camp Lejeune?
The effectiveness of this award hinges on the quality and functionality of the completed construction relative to the $16.9 million investment. If the projects address critical infrastructure gaps or enhance operational capabilities as intended, the award is effective. Regular post-award reviews and assessments of the finished facilities would provide a clearer picture of their long-term contribution to Camp Lejeune's readiness.
Industry Classification
NAICS: Construction › Nonresidential Building Construction › Commercial and Institutional Building Construction
Product/Service Code: CONSTRUCT OF STRUCTURES/FACILITIES › CONSTRUCTION OF BUILDINGS
Competition & Pricing
Extent Competed: FULL AND OPEN COMPETITION
Solicitation Procedures: SUBJECT TO MULTIPLE AWARD FAIR OPPORTUNITY
Solicitation ID: N4008506R6029
Offers Received: 4
Pricing Type: FIRM FIXED PRICE (J)
Evaluated Preference: NONE
Contractor Details
Address: 977 NORFOLK SQ, NORFOLK, VA, 23502
Business Categories: Category Business, Not Designated a Small Business
Financial Breakdown
Contract Ceiling: $16,894,195
Exercised Options: $16,894,195
Current Obligation: $16,894,195
Contract Characteristics
Commercial Item: COMMERCIAL ITEM PROCEDURES NOT USED
Cost or Pricing Data: NO
Parent Contract
Parent Award PIID: N4008506D4010
IDV Type: IDC
Timeline
Start Date: 2009-09-23
Current End Date: 2013-03-15
Potential End Date: 2013-03-15 00:00:00
Last Modified: 2021-08-05
More Contracts from Virtexco Corp
- Recoveryproject#::rm211-08::rp# Modernize Central Hvac Plant — $20.4M (Department of Defense)
- FY08 Mcon, P002, Academic Instruction Facility, Camp Geiger, AT Marine Corps Base, Camp Lejeune, North Carolina — $17.3M (Department of Defense)
- Milcon P1063 Mout Enhancements for Marine Corps Base Camp Lejeune North Carolina — $14.4M (Department of Defense)
- Base Year for the Db/Dbb GEN MAC — $13.7M (Department of Defense)
Other Department of Defense Contracts
- Federal Contract — $51.3B (Humana Government Business Inc)
- Lrip LOT 12 Advance Acquisition Contract — $35.1B (Lockheed Martin Corporation)
- SSN 802 and 803 Long Lead Time Material — $34.7B (Electric Boat Corporation)
- 200204!008532!1700!AF600 !naval AIR Systems Command !N0001902C3002 !A!N! !N! !20011026!20120430!008016958!008016958!834951691!n!lockheed Martin Corporation !lockheed Blvd !fort Worth !tx!76108!27000!439!48!fort Worth !tarrant !texas !+000026000000!n!n!018981928201!ac15!rdte/Aircraft-Eng/Manuf Develop !a1a!airframes and Spares !2ama!jast/Jsf !336411!E! !3! ! ! ! ! !99990909!B! ! !A! !a!n!r!2!002!n!1a!a!n!z! ! !N!C!N! ! ! !a!a!a!a!000!a!c!n! ! ! !Y! !N00019!0001! — $34.2B (Lockheed Martin Corporation)
- KC-X Modernization Program — $32.0B (THE Boeing Company)