Army Spends $39.8M on Herbert Hoover Dike Cutoff Wall Construction by Bauer Foundation Corp

Contract Overview

Contract Amount: $39,819,178 ($39.8M)

Contractor: Bauer Foundation Corp

Awarding Agency: Department of Defense

Start Date: 2010-05-11

End Date: 2013-10-27

Contract Duration: 1,265 days

Daily Burn Rate: $31.5K/day

Competition Type: FULL AND OPEN COMPETITION

Number of Offers Received: 3

Pricing Type: COST SHARING

Sector: Construction

Official Description: HERBERT HOOVER DIKE CUTOFF WALL

Place of Performance

Location: CLEWISTON, HENDRY County, FLORIDA, 33440

State: Florida Government Spending

Plain-Language Summary

Department of Defense obligated $39.8 million to BAUER FOUNDATION CORP for work described as: HERBERT HOOVER DIKE CUTOFF WALL Key points: 1. The Department of the Army awarded a $39.8 million contract for the Herbert Hoover Dike Cutoff Wall. 2. Bauer Foundation Corp secured the contract through full and open competition. 3. The project falls under 'Other Heavy and Civil Engineering Construction', a sector often involving significant infrastructure investment. 4. The contract was awarded as a delivery order, suggesting it's part of a larger program or framework agreement.

Value Assessment

Rating: good

The total award amount of $39.8 million for this specific delivery order appears reasonable for a large-scale civil engineering project of this nature. Benchmarking against similar dike or levee construction projects would provide a more precise assessment.

Cost Per Unit: N/A

Competition Analysis

Competition Level: full-and-open

The contract was awarded using full and open competition, which generally promotes competitive pricing and allows the government to obtain the best value. The existence of multiple bids (no: 3) indicates a competitive marketplace for this type of construction.

Taxpayer Impact: Full and open competition is the most effective method for ensuring taxpayer dollars are used efficiently, as it drives down costs through market forces.

Public Impact

Enhances flood protection for surrounding communities by reinforcing the Herbert Hoover Dike. Supports critical infrastructure maintenance and resilience in Florida. The project contributes to the local economy through construction jobs and related services. Ensures the long-term safety and stability of the dike system.

Waste & Efficiency Indicators

Waste Risk Score: 50 / 10

Warning Flags

  • Potential for cost overruns in large civil engineering projects.
  • Weather-related delays can impact project timelines and budgets.
  • Environmental compliance and permitting can add complexity and cost.

Positive Signals

  • Awarded through full and open competition, suggesting competitive pricing.
  • Project addresses critical infrastructure needs for public safety.
  • Experienced contractor (Bauer Foundation Corp) likely involved.

Sector Analysis

This project falls within the 'Other Heavy and Civil Engineering Construction' sector, which is characterized by large-scale infrastructure development. Spending in this sector can fluctuate based on government infrastructure initiatives and natural disaster recovery efforts.

Small Business Impact

While the primary contractor is Bauer Foundation Corp, it is common for large construction projects to involve numerous subcontracts. Further analysis would be needed to determine the extent of small business participation in this specific project.

Oversight & Accountability

The Department of the Army, through its contracting and project management divisions, is responsible for overseeing this project. Regular progress reports, site inspections, and adherence to contract terms are key oversight mechanisms.

Related Government Programs

  • Other Heavy and Civil Engineering Construction
  • Department of Defense Contracting
  • Department of the Army Programs

Risk Flags

  • Potential for cost overruns in large-scale construction.
  • Project duration of over 3 years may be subject to market volatility.
  • Reliance on a single contractor for a critical infrastructure component.
  • Complexity of civil engineering projects can lead to unforeseen issues.

Tags

other-heavy-and-civil-engineering-constr, department-of-defense, fl, delivery-order, 10m-plus

Frequently Asked Questions

What is this federal contract paying for?

Department of Defense awarded $39.8 million to BAUER FOUNDATION CORP. HERBERT HOOVER DIKE CUTOFF WALL

Who is the contractor on this award?

The obligated recipient is BAUER FOUNDATION CORP.

Which agency awarded this contract?

Awarding agency: Department of Defense (Department of the Army).

What is the total obligated amount?

The obligated amount is $39.8 million.

What is the period of performance?

Start: 2010-05-11. End: 2013-10-27.

What was the total value of the original contract or task order that this delivery order was a part of?

The provided data only details a specific delivery order with an award amount of $39,819,178.25. It does not specify if this was a standalone contract or a delivery order under a larger indefinite-delivery/indefinite-quantity (IDIQ) contract or basic ordering agreement. To understand the full scope and value, information on the parent contract or the overall program would be necessary.

What specific risks were identified during the bidding process that might have influenced the final price?

The data does not explicitly detail the risks identified during the bidding process. However, for large civil engineering projects like dike construction, common risks include unforeseen geological conditions, environmental compliance challenges, material cost fluctuations, and potential weather delays. The number of bids received (3) suggests some level of competition, but the specific risk assessments influencing pricing are not provided.

How does the final cost compare to the initial estimated cost for this cutoff wall construction?

The provided data does not include the initial estimated cost for the project, only the final award amount for this delivery order. Therefore, a direct comparison to determine cost efficiency or potential overruns is not possible with the given information. A cost-effectiveness analysis would require comparing the final award amount against a pre-established baseline estimate.

Industry Classification

NAICS: ConstructionOther Heavy and Civil Engineering ConstructionOther Heavy and Civil Engineering Construction

Product/Service Code: MAINT, REPAIR, ALTER REAL PROPERTYMAINT, ALTER, REPAIR NONBUILDINGS

Competition & Pricing

Extent Competed: FULL AND OPEN COMPETITION

Solicitation Procedures: SUBJECT TO MULTIPLE AWARD FAIR OPPORTUNITY

Solicitation ID: W912EP07R0006

Offers Received: 3

Pricing Type: COST SHARING (T)

Evaluated Preference: NONE

Contractor Details

Parent Company: Bauer AG (UEI: 312613391)

Address: 13203 BYRD LEGG DR, ODESSA, FL, 33556

Business Categories: Category Business, Corporate Entity Not Tax Exempt, Not Designated a Small Business, Special Designations, U.S.-Owned Business

Financial Breakdown

Contract Ceiling: $39,819,178

Exercised Options: $39,819,178

Current Obligation: $39,819,178

Contract Characteristics

Multi-Year Contract: Yes

Commercial Item: COMMERCIAL ITEM PROCEDURES NOT USED

Cost or Pricing Data: NO

Parent Contract

Parent Award PIID: W912EP07D0011

IDV Type: IDC

Timeline

Start Date: 2010-05-11

Current End Date: 2013-10-27

Potential End Date: 2013-10-27 00:00:00

Last Modified: 2021-03-28

More Contracts from Bauer Foundation Corp

View all Bauer Foundation Corp federal contracts →

Other Department of Defense Contracts

View all Department of Defense contracts →

Explore Related Government Spending