Army Awards $28.9M for Herbert Hoover Dike Cutoff Wall to Bauer Foundation Corp
Contract Overview
Contract Amount: $28,892,526 ($28.9M)
Contractor: Bauer Foundation Corp
Awarding Agency: Department of Defense
Start Date: 2008-05-22
End Date: 2011-02-11
Contract Duration: 995 days
Daily Burn Rate: $29.0K/day
Competition Type: FULL AND OPEN COMPETITION
Number of Offers Received: 1
Pricing Type: FIRM FIXED PRICE
Sector: Construction
Official Description: HERBERT HOOVER DIKE CUTOFF WALL
Place of Performance
Location: CLEWISTON, HENDRY County, FLORIDA, 33440
State: Florida Government Spending
Plain-Language Summary
Department of Defense obligated $28.9 million to BAUER FOUNDATION CORP for work described as: HERBERT HOOVER DIKE CUTOFF WALL Key points: 1. Spending on the Herbert Hoover Dike Cutoff Wall project reached $28.9 million. 2. Bauer Foundation Corp was awarded the contract. 3. The contract was awarded under full and open competition. 4. The project falls under the 'Other Heavy and Civil Engineering Construction' sector.
Value Assessment
Rating: good
The awarded amount of $28.9 million appears reasonable given the scope of a major dike cutoff wall construction. Benchmarking against similar large-scale civil engineering projects would provide a more precise assessment.
Cost Per Unit: N/A
Competition Analysis
Competition Level: full-and-open
The contract was awarded through full and open competition, suggesting a robust price discovery process. This method typically leads to competitive pricing as multiple bidders vie for the contract.
Taxpayer Impact: Full and open competition generally ensures taxpayer funds are used efficiently by driving down costs through market forces.
Public Impact
Enhances the structural integrity and safety of the Herbert Hoover Dike. Contributes to flood risk reduction for surrounding communities. Supports critical infrastructure maintenance and improvement efforts.
Waste & Efficiency Indicators
Waste Risk Score: 50 / 10
Positive Signals
- Full and open competition utilized
- Clear project objective for infrastructure improvement
Sector Analysis
This project falls within the heavy and civil engineering construction sector, which involves large-scale infrastructure development. Spending benchmarks for similar dike or levee reinforcement projects would be relevant for comparison.
Small Business Impact
The data indicates that small businesses were not directly awarded this contract, as it went to Bauer Foundation Corp. Further analysis would be needed to determine if small businesses participated as subcontractors.
Oversight & Accountability
The Department of the Army, under the Department of Defense, is responsible for overseeing this contract. Standard procurement oversight processes should be in place to ensure project completion and adherence to contract terms.
Related Government Programs
- Other Heavy and Civil Engineering Construction
- Department of Defense Contracting
- Department of the Army Programs
Risk Flags
- Lack of detailed cost breakdown
- Absence of performance metrics
- No information on potential environmental impacts
Tags
other-heavy-and-civil-engineering-constr, department-of-defense, fl, delivery-order, 10m-plus
Frequently Asked Questions
What is this federal contract paying for?
Department of Defense awarded $28.9 million to BAUER FOUNDATION CORP. HERBERT HOOVER DIKE CUTOFF WALL
Who is the contractor on this award?
The obligated recipient is BAUER FOUNDATION CORP.
Which agency awarded this contract?
Awarding agency: Department of Defense (Department of the Army).
What is the total obligated amount?
The obligated amount is $28.9 million.
What is the period of performance?
Start: 2008-05-22. End: 2011-02-11.
What was the initial estimated cost versus the final awarded cost?
The provided data does not include the initial estimated cost. The final awarded amount is $28,892,525.53. A comparison between the estimate and the final award would reveal potential cost efficiencies or overruns during the procurement process.
Were there any performance issues or contract modifications during the project lifecycle?
The data does not detail performance issues or contract modifications. Information on project execution, change orders, and contractor performance would be necessary to assess the overall effectiveness and identify any potential risks encountered during the contract period.
How does the per-unit cost of this project compare to similar dike construction projects?
A specific per-unit cost benchmark is not available without more detailed project specifications and comparable contract data. The total contract value of $28.9 million for a cutoff wall suggests a significant investment, and its cost-effectiveness is best evaluated against similar large-scale civil engineering undertakings.
Industry Classification
NAICS: Construction › Other Heavy and Civil Engineering Construction › Other Heavy and Civil Engineering Construction
Product/Service Code: MAINT, REPAIR, ALTER REAL PROPERTY › MAINT, ALTER, REPAIR NONBUILDINGS
Competition & Pricing
Extent Competed: FULL AND OPEN COMPETITION
Solicitation Procedures: ONLY ONE SOURCE
Solicitation ID: W912EP07R0006
Offers Received: 1
Pricing Type: FIRM FIXED PRICE (J)
Evaluated Preference: NONE
Contractor Details
Parent Company: Bauer AG (UEI: 312613391)
Address: 13203 BYRD LEGG DR, ODESSA, FL, 33556
Business Categories: Category Business, Corporate Entity Not Tax Exempt, Not Designated a Small Business
Financial Breakdown
Contract Ceiling: $28,892,526
Exercised Options: $28,892,526
Current Obligation: $28,892,526
Contract Characteristics
Commercial Item: COMMERCIAL ITEM PROCEDURES NOT USED
Cost or Pricing Data: NO
Parent Contract
Parent Award PIID: W912EP07D0011
IDV Type: IDC
Timeline
Start Date: 2008-05-22
Current End Date: 2011-02-11
Potential End Date: 2011-02-11 00:00:00
Last Modified: 2021-03-28
More Contracts from Bauer Foundation Corp
- Center Hill Foundation Remediation — $122.0M (Department of Defense)
- Moose Creek DAM Modification — $101.5M (Department of Defense)
- HHD Matoc Cutoff Wall Construction — $72.5M (Department of Defense)
- HHD to 0005 — $51.6M (Department of Defense)
- Conventional Cutoff Wall — $50.5M (Department of Defense)
Other Department of Defense Contracts
- Federal Contract — $51.3B (Humana Government Business Inc)
- Lrip LOT 12 Advance Acquisition Contract — $35.1B (Lockheed Martin Corporation)
- SSN 802 and 803 Long Lead Time Material — $34.7B (Electric Boat Corporation)
- 200204!008532!1700!AF600 !naval AIR Systems Command !N0001902C3002 !A!N! !N! !20011026!20120430!008016958!008016958!834951691!n!lockheed Martin Corporation !lockheed Blvd !fort Worth !tx!76108!27000!439!48!fort Worth !tarrant !texas !+000026000000!n!n!018981928201!ac15!rdte/Aircraft-Eng/Manuf Develop !a1a!airframes and Spares !2ama!jast/Jsf !336411!E! !3! ! ! ! ! !99990909!B! ! !A! !a!n!r!2!002!n!1a!a!n!z! ! !N!C!N! ! ! !a!a!a!a!000!a!c!n! ! ! !Y! !N00019!0001! — $34.2B (Lockheed Martin Corporation)
- KC-X Modernization Program — $32.0B (THE Boeing Company)